image


Transportation Resource Oversight Committee Meeting (Lake & Porter Counties)

Tuesday, September 18, 2018 9:00 am CST at NIRPC Office


Agenda


  1. Welcome, Pledge of Allegiance


  2. Meeting Minutes of August 28, 2018

    ACTION REQUESTED: Approval


  3. FY 19-22 Spending Plan Update

    See handout to be provided before meeting


  4. Project Requests

    1. Request for Change of Year; 1702159 Lake County; PE – $116,000 federal ($145,000 total); move from FY 18 to FY 19.


  5. NOFA Guidelines / Instructions

    ACTION REQUESTED: Discussion

    See handout to be provided before meeting


  6. Letting results

    1. 1382594 – Cedar Lake; To be Announced


  7. Other New Business


  8. Public Comments


  9. Adjournment. Next meeting is October 23, 2018 @ 9AM NIRPC Offices


If anyone cannot attend the meeting but would like to participate via teleconference please contact Charles Bradsky at 219-254-2509 or cbradsky@nirpc.org and request the NIRPC’s conference call in number and access code. This request must be made for each meeting and at least 24 hours in advance.

Transportation Resource & Oversight Committee Lake & Porter Counties

6100 Southport Road, Portage August 28, 2018 Meeting Minutes


In attendance were Greg Falkowski (Crown Point), Dave Uran (Crown Point), George Topoll (NIRPC Comissioner), Mark Gordish (Hammond), Dean Button (Hammond), Duane Alverson (Lake County), Sandy Kolb (Portage), Jeff Huet (Schererville), Tyler Kent (Valparaiso), Mark O’Dell (Chesterton), Kelly Wenger (NICTD), Bob Thompson (Porter County), Phil Gralik (Hobart), Trisha Nugent, Eric Wolverton, Jake Dammarell and Dennis Cobb. Joyce Newland (FHWA) participated via conference phone.

NIRPC staff included Charles Bradsky, Trey Wadsworth, Domonique Edwards and Candi Eklund. Charles Bradsky called the meeting to order at 9:06 a.m. with the Pledge of Allegiance.

Approval of Minutes

The minutes of the July 24, 2018 meeting were approved as presented on motion by Dean Button and second by Jeff Huet.


FY 19-22 Spending Plans Ad-Hoc Committee Solution/Update

Dean Button began the meeting by asking Charles Bradsky if the TROC meetings required a Full Commission member be present. Charles stated it is not a requirement. Dean thanked Charles for the clarification.


Charles Bradsky distributed the newly created Scenario B Spending Plan to the committee. This new plan, if adopted, would bring the budget in FY 2019 down to a deficit of $43,000 and a deficit of $985,190 in FY 2020. Charles stated these shortfalls could possibly be rectified with the funding allocated towards change orders. Charles also informed the committee that NIRPC received additional bonus funds in the amount of $960,612 from INDOT. These additional funds might allow the project for Ransom Road (des

# 1601159) in Valparaiso to move back into FY 2019. Also, Winfield reported at the Local Quarterly Meeting that they could be ready to accelerate their project to FY 2019 to free up funding in 2020.


Dennis Cobb inquired why the Right of Way for des # 1601146, the Marquette Trail project in East Chicago, had been eliminated. Charles explained the project had been eliminated in Amendment #10, but he will discuss further with William Allen for further clarification.


Duane Alverson spoke to the 45th avenue project, DES # 990080, moving to FY 2022. Duane wanted to reiterate his understanding of insuring any project moving beyond the 2018-2021 TIP, would be given first priority in the 2020-2023 TIP without going through the selection process again.


Charles Bradsky updated the committee on the acceptance taken by the Full Commission on the two Gary projects discussed at the previous TROC meeting. The two projects totaled $5,060,000. Charles will move Des #1172078 to FY 2021 and 2022. In the October Amendments, NIRPC will present the Ridge Road project for Gary be eliminated. The two new projects for Gary will be incorporated into the TIP. Eric Wolverton asked if the two projects for Gary could switch their fiscal year’s in the spending plan. Charles will discuss these changes with Eric.

Bob Thompson questioned his project for Porter County, DES #1401029, being moved to FY 2020 from FY 2019. Charles will investigate this project and discuss with Bob. Point of information. This was a mistake and it will be left in FY 19 since this is important to Porter County.


There was a motion by Jeff Huett and a second by Dean Button to continue processing and developing the new Scenario B Spending Plan.

There were no Letting results to report for this month. New Business

The town of Portage requested $84,836 for project #0900080. Sandy Kolb of Portage, asked for this

request to be tabled until the next meeting due to further coordinated construction costs.


Public Comments

With the draft policy for Project Substitution and Scope Change Policies being discussed at the Full Commission meeting in August 2018, Dean Button requested the policy be amended by the TROC Committee and included as an agenda item at the next TPC Committee meeting for their recommendations. The draft policy was approved by the Lake and Porter Counties in November 2017 but was not approved by LaPorte County. Trey Wadsworth stated the same set of rules needs to apply across all three counties.


On motion by Mark O’Dell and second by Dean Button, the TROC committee approved the verbiage in this document to be changed from ‘at least five years, to ‘no more than four years’.


On motion by Dean Button and second by Mark O’Dell, the TROC committee voted to present the amended scope change policy at the next TPC meeting for adoption to review and present recommendations.


The Fiscal Management Information Systems (FMIS) letters being sent to INDOT needs to be submitted to Charles by September 10, 2018. If submitted after this date, they will have to wait a month for any FMIS approval letters.


The new bike maps are now available and several communities picked them up after the meeting.


Dominique Edwards discussed the two remaining pop up events for the 2050 plan during public engagements. There will be additional pop up events for the 2050 plan in the fall at some of the local harvest markets.


Adjournment

There being no further business, the meeting adjourned at 10:09 a.m.

The next meeting will be held on September 18, 2018, the third Tuesday, at 9:00 a.m.

Northwestern Indiana Regional Planning Commission

Blue Text - Most recent proposal

MPO funds only - 2018-2021 LPA highway projects: Chicago UZA

7/13/2018

< last updated

Green Text - After discussing with municipal officials, this must stay where it is.

Includes all amendment changes & proposed amendment #10 changes

Red Text - Projects that haven't moved that are at higher risk

image


Row ID

Des #

Sponsor

Route

Work Type

Location

Letting Date

Federal Fund Type

Year

Phase

In TIP or SPMS

Only

Risk

Comments

TIP 2019

Actual Obligated 2018

TIP 2020

TIP 2021

2022

Post-TIP

Quarterly Notes / Comments

STBG

CMAQ

HSIP

TA

STBG

CMAQ

HSIP

TAP/TE-TA

STBG

CMAQ

HSIP

TA

STBG

CMAQ

HSIP

TA

All sources

39

0401062

Schererville

Pennsy Greenway

Bicycle & Pedestrian Facilities

Acquistion

STBG I

Chicago UZA

2019

2_ RR

$ 308,000

2_Low

4/6 Moved from FY 18; per INDOT/JG

$ 308,000

18 Q3 - Will move these funds to 1382661 [phase 3], but waiting until Phase 3 is ready. AM to come later.

40

1601164

Hammond

Pedestrian Flashing Beacons, Installed

at 3 trail crossings

1/18/2018

HSIP Chicago UZA

2019

3_CN

$ 23,448

1_Zero Obligated

Engineer's bid -

$232,875 low bid -

$194,390.29 NIRPC

obligated

$174,951.00 for CN &

$18,039.00 for CE

$ 23,448

41

1601146

East Chicago

Marquette Trail

Bike/Pedestrian Facilities

from Indinapolis Blvd. (US

20) to Kennedy Ave

10/15/2019

CMAQ Chicago UZA

2018

1_PE

$ 247,840

1_Zero Obligated

2/1/18 EC to get RFP and contract ASAP to obligate these funds in 2018. 4/3 scoring RFPs 4/25 moved to FY 19 per INDOT/MB

$ 247,840

18 Q3 - Had trouble getting RFP for PE. Would like to move funding to FY 19…but NIRPC does not have the funds.

42

1173595

Schererville

Pennsy Greenway

Bicycle & Pedestrian Facilities

Pennsy Greenway P2. Main St to 137th Ave.

12/12/2018

STBG I

Chicago UZA

2019

3_CN

$ 680,960

3_ Med Funds

Q3LQR - CN est

$870,000 ($696,000 fed) CE $130,500

($104,400 fed)

$ 680,960

18 Q3 - costs are up but town will cover.

43

12/12/2018

STBG I

Chicago UZA

2019

4_CE

$ 119,040

$ 119,040

44

12/12/2018

TAP Chicago UZA

2019

3_CN

$ 387,000

$ 387,000

19 Q3 - costs are up but town will cover.

45

1173760

Schererville

Kennedy Ave

Added Travel Lanes

Kennedy Ave at Junction St. South to 67th St. and then South to US 30

12/12/2018

STBG I

Chicago UZA

2019

2_RW

$ 200,000

$ 200,000

18 Q3 - Costs are up but keep funding the same. Some funding may come from 1382603.

46

1382594

Cedar Lake

Lake Shore Drive

Intersect. Improvements (Roundabout)

at Cline Ave

9/12/2018

STBG I

Chicago UZA

2019

3_CN

$ 1,500,000

2_Low

Q3LQR - STG3 CN est $1,722,282.09 ($1,377,825,67 fed) CE $187,500 ($122,174.33 fed)

$ 1,500,000

18 Q3 - STG 3 revised in Permits, ROW good. Minor Q: with Hydraulics. No big issues

47

1382661

Schererville

Pennsy Greenway

Bicycle & Pedestrian Facilities

Pennsy Greenway, P3 from Wilhelm Street at Schererville Town Hall to 213th Street

3/6/2019

STBG I

Chicago UZA

2019

3_CN

$ 1,278,000

3_Med Schedule

Q3LQR - CN est

$1,397,813 ($1,118,250.40 fed) CE $199,687 ($159,749.6 fed)

$ 1,278,000

18 Q3 - Will move RR funds from 0401062. AM to come later. Some RR issues.

48

1401029

Porter County

CR 100S

Intersec. Improvement

CR 100S-2000 W of CR725 Wto 1000 E of CR 500W

3/6/2019

STBG I

Chicago UZA

2019

1_PE

$ 652,000

2_Low

$ 652,000

18 Q3 - HSIP funds?? SPMS shows $652,000 Group I funds and $427,888 Group IV funds

49

1401030

Crown Point

126th Ave (Burrell Dr)

Intersect. Improv. W/ Added Turn Lanes

From SR 55 to Court St

12/12/2018

HSIP Chicago UZA

2019

3_CN

$ 1,403,046

2_Low

CE-$155,894 fed

$ 403,046

18 Q3 - ROW is on track; 6/22 STG 3 estimate CN $1.54 M total & CE $192K total ($1,558,800 HSIP funds) Need $156K

50

PYB Chicago UZA

$ 1,000,000

51

1500323

Crown Point

US 231

Other Intersection Improvement

Courthouse Square, construct pedestrian bump- outs

7/11/2018

HSIP Chicago UZA

2019

3_CN

$ 516,380

1_Zero Obligated

Low bid CN

$529,951.1 ($24,598.40 INDOT) ($454,817 fed); CE

$68,403.34 ($61,563

fed)

$ 516,380

$ 516,380

18 Q3 - In Contracts. INDOT wants city to add ped signals; to be paid for by INDOT. Verify this when contract lets. Winning contact $529,951.10

52

1500416

Hammond

US 41

Bike/Pedestrian Bridge

over US 41 near Conkey St

7/11/2018

TAP Chicago UZA

2019

3_CN

$ 2,000,000

1_Zero Obligated

AM 9/17 Added

$494,000 for CE. Q3LQR- CN est

$4,557,408 ($2,000,000 fed) CE

$520,000 ($416,000

fed)

$ 2,043,600

$ 2,043,600

18 Q3 - $494,000 for CE given by Gary Evers (AM 9/17), but not in TIP or Spending Plan; Discuss at TROC

53

2019

4_CE

$ 494,000

1_Zero Obligated

$ 416,000

$ 416,000

18 Q3 - $494,000 for CE given by Gary Evers (AM 9/17), but not in TIP or Spending Plan; Discuss at TROC

55

1592274

Highland

Signage on multiple trails, installed

Multiple Trails; Multiple LPA's

1/16/2019

TAP Chicago UZA

2019

3_CN

$ 800,000

2_Low

$36,320 ($29,056 fed

for CE)

$ 800,000

18 Q3 - Letting moving to 1/16/19 because of NEPA doc, STG 3 due 8/24/18, RFC is 11/7/18. 18 Q4 - GTG

56

1592275

Hobart

Environmental Mitigation

Deep River Stormwater Outfall and BMP.

7/10/2019

TAP Chicago UZA (E&W)

2019

1_PE

$ 36,000

marcia and I to investigate

$ 36,000

18 Q3 - On Schedule

57

1592420

Merrillville

Install Signal Pre- Emption Devices 1

All signals in Hobart, Crown Point, Schererville, Merrillville, Dyer, Griffith, St. John

10/11/2018

HSIP Chicago UZA

2019

3_CN

$ 795,515

2_Low

Combined line 74

with line 75,

(2,135,869 +1017563

= 3,153,432) Q3LQR - CN est $1,752,140 ($1,576,926) CE $0

$ 795,515

18 Q3 - Minimal Risk. Move letting one month (to 10/11/18) due to agreement with RR at one location.

New estimate CN - TC $3,628,767 $2,725,616 is PYB monies. See email strings on 2/23

58

PYB Chicago UZA

$ 1,725,616

$ 1,725,616

59

Sec 164

$ 632,301

$ 632,301

60

1600418

Gary

Airport Rd

Road Rehab (3R/4R Standards)

Airport Road 3R/4R Reconstruction: Cline Ave to EJ&E RR Bridge Phase 3

1/16/2019

STBG I

Chicago UZA

2019

3_CN

$ 3,500,000

2_Low

verify date January 2019

$ 3,500,000

18 Q3 - Gary want to accelerate to FY 19 (April '19) but told that may not happen; TROC to discuss.

61

1600632

Gary PTC

FTA Transfers

CMAQ Demo Operating Assistance

Broadway Express Year

#3

CMAQ Chicago UZA

2019

5_5_FL EX

$ 894,822

1_Zero Obligated

$ 894,822

62

1601146

East Chicago

Marquette Trail

Bike/Pedestrian Facilities

from Indinapolis Blvd. (US 20) to Kennedy Ave

10/15/2019

CMAQ Chicago UZA

2019

2_RW

$ 24,000

2_Low

No ROW is needed; See Amend #10

18 Q3 - I parcel of ROW is needed, agreement with NIPSCO no purchase

63

1601147

Burns Harbor

Marquette Trail

Bike/Pedestrian Facilities

Marquette Greenway Trail,

8/5/2020

CMAQ Chicago

2019

2_RW

$ 12,000

2/8/18 No ROW is

N/A

SR149 to Babcock Rd

UZA

needed. See Amend

#10

64

1601157

Crown Point

109th Ave

Access Control

109th Ave Access Control, Delaware Pkwy to SR 53, includes median construction

10/15/2019

HSIP Chicago UZA

2019

2_RW

$ 101,250

2_Low

could this qualify for CMAQ?

$ 101,250

18 Q3 - On schedule; City would like to accelerate if possible

66

1601159

Valparaiso

Ransom Rd

Other Type Project (Miscellaneous)

Ransom Road Safety Improvements, CR50W to CR 150W

11/15/2018

HSIP Chicago UZA

2019

2_RW

$ 23,400

RW to be eliminated Amend #10 funds to be applied to CN

N/A

67

1601159

Valparaiso

Ransom Rd

Other Type Project (Miscellaneous)

Ransom Road Safety Improvements, CR50W to CR 150W

12/12/2018

HSIP Chicago UZA

2019

3_CN

$ 476,361

3_Med Funds

Valpo requesting and additional $33,741 for CE/CN Q3LQR CN

est $465,800 ($419,220 fed) CE

$69,100 ($62,190

fed)

$ 476,361

18 Q3 - Accelerated from 11/20. City would like additional funds for Mill & Fill, & Rumble Stripes to be discussed at TROC.

68

1601161

Kouts

Regulatory & Warning Sign Replacement

Town-wide

7/11/2018

HSIP Chicago UZA

2019

3_CN

$ 40,500

1_Zero Obligated

Low bid CN

$38,594.08 ($34,735

fed); CE $9,000 ($8,190 fed)

$ 42,925

$ 42,925

18 Q3 - In Contracts CE? Originally put CE in with PE (big No-No) for CE is $9,100 TC ($8,190 fed) Winning bid at letting is $38594.08 ($34,735 fed)

69

1601162

Kouts

Pavement Markings

Town-wide

7/11/2018

HSIP Chicago UZA

2019

3_CN

$ 11,700

2_Low

No bids

$ 11,700

$ -

18 Q3 - In Contracts CE? Originally put CE in with PE (big No-No) for $9,100 TC ($7,280)

Row ID

Des #

Sponsor

Route

Work Type

Location

Letting Date

Federal Fund Type

Year

Phase

In TIP or SPMS

Only

Risk

Comments

TIP 2019

Actual Obligated 2018

TIP 2020

TIP 2021

2022

Post-TIP

Quarterly Notes / Comments

70

1601163

Hammond

173rd Ave

Pedestrian Island Construction

at Main Entrance to Purdue NW Campus

8/14/2019

STBG I

Chicago UZA

2019

2_RW

$ 40,000

2-Low

$ 40,000

18 Q3 - May not need; but keep on the books just in case

71

1601184

Valparaiso

FTA Transfers

CMAQ Demo Operating Assistance

V-Line Porter Hospital (Year #1)

CMAQ Chicago UZA

2019

5_5_FL EX

$ 332,800

1_Zero Obligated

$ 332,800

72

1601185

Valparaiso

FTA Transfers

CMAQ Demo Operating Assistance

CMAQ Demo Chicago DASH Bus #5 (Year #1)

CMAQ Chicago UZA

2019

5_5_FL EX

$ 275,200

1_Zero Obligated

$ 275,200

73

1601923

Portage

Willowcreek Road

Bridge Rehabilitation Or Repair

Rehabilitate Willowcreek Rd Bridge over I-80/90.

7/11/2018

STBG I

Chicago UZA

2019

3_CN

$ 640,000

1_Zero Obligated

$ 525,671

$ 525,671

18 Q3 - In Contracts. Letting Low bid $657,088.16 ($525,671 fed) CE- $0.00

74

1702158

Gary

Marquette Trail

Bike/Pedestrian Facilities

Gary Green Links/Marquette Trail. Roosevelt St to Polk St.

11/11/2020

STBG I

Chicago UZA

2019

1_PE

$ 300,000

2_Low

$ 300,000

18 Q3 - On schedule

30

1702159

Lake County

101st Ave

Signals, New or Improved

101st Ave New Signals at Sheffield Ave.

7/10/2019

STBG I

Chicago UZA

2018

1_PE

$ 116,000

2018

$ 116,000

Moved to 2019

75

1702159

Lake County

101st Ave

Signals, New or Improved

101st Ave New Signals at Sheffield Ave.

7/10/2019

STBG I

Chicago UZA

2019

2_RW

$ 20,000

3_Med

2019

$ 20,000

18 Q3 - keep here, Revisit next LQM.

78

0900075

Valparaiso

Silhavy Rd

Rebuild 3R/4R

Evans Ave to LaPorte Ave

2/6/2019

STBG I

Chicago UZA

2019

3_CN

$ 3,094,579

2_Low

*Admin Mod Mar 18* change date from FY 21 to FY 19

$ 3,094,579

18 Q3 - ROW has 2 condemnations; CN RR

79

0900075

Valparaiso

Silhavy Rd

Rebuild 3R/4R

Evans Ave to LaPorte Ave

2/6/2019

STBG I

Chicago UZA

2019

4_CE

$ 464,181

2_Low

$ 464,181

18 Q3 - ROW has 2 condemnations; CN RR

80

0900080

Portage

Central Ave

Access Control

Willowcreek Rd Intersection Improvements at Central Ave.

1/16/2019

CMAQ Chicago UZA

2019

3_CN

$ 1,152,000

2_Low

*Admin Mod Mar 18* change date from FY 18 to FY 19 Q3LQR- CN est $1,260,000 ($1,008,000 fed) CE

$189,000 ($151,200

fed)

$ 1,152,000

Admin Mod 9/17 added funds to this project. From $1,089,760 to $1,152,000 (fed) 18 Q3 - ROW in Condemnation; STG3 6/18;

81

NIRPC

CMAQ Planning

Public Education SFY 2019

CMAQ Chicago UZA

2019

6_6_6_ UPW P

$ 360,000

1_Zero Obligated

$ 360,000

82

1172007

Lake County

45th Ave

Added Travel Lanes

45th Ave. from Whitcomb to Chase (Ph 2B)

12/12/2018

STBG I

Chicago UZA

2019

3_CN

$ 1,752,000

4_High Schedule

high risk for FY 19; CN est $1,950,000 ($1,560,000 Fed) CE

$243,750 ($192,000

fed)

$ 1,752,000

18 Q3 - Lake County wants to move to FY 20; need to verify ROW amounts

50

1401034

Hobart

Colorado St

Line of Sight Corrections; Access Management

North of US 30

1/15/2020

HSIP Chicago UZA

2020

2_RW

$ 56,250

4_High Funds

Amend #10 added phase

$ 56,250

18 Q3 - ROW current needs equal $195,000. 18 Q4 - Project costs are starting to escalate. ROW- 4X; CN- 2X. Advised to talk to INDOT since they control this intersection.

54

1592273

Lowell

Bicycle & Pedestrian Equipment

Up to 20 Bicycle Racks

CMAQ Chicago UZA

2019

1_PE

$ 1,600

3_Med

to be moved to 2019 per MB. Need to be put into Admin Mod 4/3

$ 1,600

18 Q3 - Town still wants to continue but informed that there may not be funds.

65

1601158

Crown Point

109th Ave

Intersect. Improvements (Roundabout)

at Iowa St

7/14/2021

HSIP Chicago UZA

2019

2_RW

$ 112,500

4_High Schedule

If PE is in late 2018 & CN is in 2022, RW probably will be moved out to 2020

$ 112,500

18 Q3 - City would like to move this phase to FY 20

76

0710056

Munster

45th St

Railroad Grade Separation & Added Travel Lanes

Reconstruction of 45th St from 0.2 mi E of Calumet Ave to Calumet Ave

3/6/2019

PYB Chicago UZA

2019

3_CN

$ 6,980,644

4_High Schedule Complexity

$ 6,980,644

18 Q3 - INDOT, RDA, NIRPC funds. Moving along, USPs better; big issue with shoefly (RR want town to build, INDOT feels not a good idea). If it getts bumped, it will probably be to FY 22 or 23.

77

0710056

Munster

45th St

Railroad Grade Separation & Added Travel Lanes

Reconstruction of 45th St from 0.2 mi E of Calumet Ave to Calumet Ave

3/6/2019

STBG I

Chicago UZA

2019

3_CN

$ 2,619,356

4_High Schedule Complexity

*Admin Mod Mar 18* change date from FY 18 to FY 19

$ 2,619,356

18 Q3 - INDOT, RDA, NIRPC funds. Moving along, USPs better; big issue with shoefly (RR want town to build, INDOT feels not a good idea).

image

Row ID

Row ID

image

image



83

Des #


1006787

Sponsor


Merrillville

Route


Mississippi St

Work Type


Added Travel Lanes

Location


93rd Ave to 101st Ave

Letting Date


7/10/2019

Federal Fund Type

Year


2020

Phase


3_CN

In TIP or SPMS

Only


$ 3,612,000

Risk


4_Funds

Comments


Amend #10 added phase CN est

$4,516,000 ($3,612,000 fed) CE

$0

TIP 2019

Actual Obligated 2018

TIP 2020

TIP 2021

2022

Post-TIP

Quarterly Notes / Comments

STBG I

Chicago UZA

$ 3,612,000

18 Q3 - Good. Minimal risk to schedule, funds or scope. Candidate for Plan B 2019 letting. 18 Q4 - Town would like to move this project back one year to come up with the money and get more life out of pavment.

85

1173707

Munster

Pennsy Greenway

Bicycle & Pedestrian Facilities

Construct Pennsy Greenway Trail from Fisher St at Timrick Dr to Calumet Ave north of 45th St

7/10/2019

CMAQ Chicago UZA

2020

3_CN

$ 555,040

2_Low

$ 555,040

18 Q3 - Need a new estimate since project is being tweaked and may combine with 1173597. Funds may move to 1173597 and move to 2022.

86

1173760

Schererville

Kennedy Ave

Added Travel Lanes

Kennedy Ave at Junction St. South to 67th St. and then South to US 30

2/5/2020

STBG I

Chicago UZA

2020

3_CN

$ 4,206,472

2_ Low Funds

Q3LQR- CN est

$5,834,000 ($4,206,472[72%]) CE $875,000 ($0 fed)

$ 4,206,472

18 Q3 - Costs are up but keep funding the same. Some funding may come from 1382603.

89

1500221

Hammond

Chicago Ave

Added Travel Lanes

from IN/IL State Line to Marble St

7/10/2019

STBG I

Chicago UZA

2020

3_CN

$ 9,400,000

2_Low

Q3LQR- CN est

$10,000,000 ($8,355,556 fed) CE

$1,305,556 ($1,044,444 Fed) =

$11,791,713($9,433,

369 fed)

$ 9,400,000

18 Q3 - Funds for RR are in PE

91

1592275

Hobart

Environmental Mitigation

Deep River Stormwater Outfall and BMP.

7/10/2019

TAP Chicago UZA

2020

3_CN

$ 246,480

2_Low

$ 246,480

18 Q3 - On track. 18 Q4 - Cost are expecting to rise.

92

1601146

East Chicago

Marquette Trail

Bike/Pedestrian Facilities

from Indinapolis Blvd. (US

20) to Kennedy Ave

10/15/2019

CMAQ Chicago UZA

2020

3_CN

$ 828,000

3_Med Schedule

Amend #10 added phase

$ 828,000

18 Q3 - Letting needs to move to FY21.

93

1601157

Crown Point

109th Ave

Access Control

109th Ave Access Control, Delaware Pkwy to SR 53, includes median construction

10/15/2019

HSIP Chicago UZA

2020

3_CN

$ 1,098,000

2_Low

*Admin Mod Mar 18* LQR, SPMS shows letting is 10/9/19 (in 2021 TIP) CN est

$1,220,000 ($1,098,000 Fed) CE

$152,000 ($122,000

Fed)

$ 1,098,000

18 Q3 - City would like to accelerate if possible.

94

1601163

Hammond

173rd Ave

Pedestrian Island Construction

at Main Entrance to Purdue NW Campus

8/14/2020

STBG I

Chicago UZA

2021

3_CN

$ 792,000

3_Med Funds

Q3LQR- CN est

$573,913 ($459,130 fed); CE $56,087

($68,870 fed)

$ 792,000

18 Q3 - City requesting additional funds for scope revision (bus turnout spot) PE and CN.

95

1601165

Gary

Regulatory & Warning Sign Replacement

City-wide

7/10/2019

HSIP Chicago UZA

2020

3_CN

$ 450,000

2_Low

$ 450,000

18 Q3 - RFP in process

96

1601184

Valparaiso

FTA Transfers

CMAQ Demo Operating Assistance

V-Line Porter Hospital (Year #2)

CMAQ Chicago UZA

2020

5_5_FL EX

$ 326,400

1_Zero Obligated

$ 326,400

97

1601185

Valparaiso

FTA Transfers

CMAQ Demo Operating Assistance

CMAQ Demo Chicago DASH Bus #5 (Year #2)

CMAQ Chicago UZA

2020

5_5_FL EX

$ 269,600

1_Zero Obligated

$ 269,600

98

1601726

Winfield

Randolph St

Other Type Project (Miscellaneous)

Randolph St HAWK Signal (2000' S of 109th)

8/7/2019

HSIP Chicago UZA

2020

3_CN

$ 70,200

3_Med Funds

$ 70,200

18 Q3 - All projects on one CN contract. CN cost increased from TC $78,000 ($70,200 fed) to TC $125,000 ($112,500 fed). Candidate for Plan B 2019 letting.

99

1601727

Winfield

Randolph St

Other Type Project (Miscellaneous)

Randolph St School Zone Flashers (3000' & 4000' S of 109th)

8/7/2019

HSIP Chicago UZA

2020

3_CN

$ 9,000

3_Med Funds

$ 9,000

18 Q3 - All projects on one CN contract. CN cost increased from TC $10,000 ($9,000 fed) to TC $16,000 ($14,400 fed). Candidate for Plan B 2019 letting.

100

1601728

Winfield

109th Ave

Signage, New or Replacement

109th Ave Signage Improvements (109th, 5600' W of Randolph)

8/7/2019

HSIP Chicago UZA

2020

3_CN

$ 5,400

3_Med Funds

$ 5,400

18 Q3 - All projects on one CN contract. CN cost increased from TC $6,000 ($5,400 fed) to TC $8,000 ($7,200 fed). Candidate for Plan B 2019 letting.

101

1702159

Lake County

101st Ave

Signals, New or Improved

101st Ave New Signals at Sheffield Ave.

7/10/2019

STBG I

Chicago UZA

2020

3_CN

$ 391,000

3_ Med Schedule

Q3LQR- CN

$500,000 ($400,000

fed) CE $75,000 ($3,000 fed)

$ 391,000

18 Q3 - keep here, Revisit next LQM.

103

NIRPC

CMAQ Planning

Public Education SFY 2020

CMAQ Chicago UZA

2020

6_6_6_ UPW P

$ 360,000

1_Zero Obligated

$ 360,000

82

1173430

Portage

Central Ave

Road Reconstruction (3R/4R Standards)

Central Ave. reconstruction from Lake/Porter Co. Line to Willowcreek Road

7/8/2020

STBG I

Chicago UZA

2020

2_RW

$ 200,000

4_High Scope

*Admin Mod Mar 18* change date from FY 18 to FY 20

$ 200,000

18 Q3 - project will be split in tow or more phases by next LQM.

84

1172078

Gary

Ridge Rd

Road Reconstruction (3R/4R Standards)

Ridge Road Reconstruction, Connecticut St to Mississippi St. Phase 2

7/10/2019

STBG I

Chicago UZA

2020

3_CN

$ 5,060,000

4_High Scope

$ 5,060,000

18 Q3 - Gary to rescope

87

1382598

Hobart

County Line Rd

Road Reconstruction (3R/4R Standards)

from US 6 to Cleveland Ave

10/7/2020

STBG I

Chicago UZA

2020

2_RW

$ 200,000

4_High Schedule

$ 200,000

18 Q3 - NEPA doc is outstanding. FHWA & SHPO have issues. May need to move 12 months.

88

1401034

Hobart

Colorado St

Line of Sight Corrections; Access Management

North of US 30

1/15/2020

HSIP Chicago UZA

2020

3_CN

$ 734,850

4_High Funds

*Admin Mod Mar 18* LQR, SPMS shows letting is 10/19/19 (in 2021 TIP)

$ 734,850

18 Q3 - ROW current needs equal $195,000 18 Q4 - Updated ROW cost are $571,000, updated CN cost is

$1,620,000 18 Q4 - Project costs are starting to escalate. Advised to talk to INDOT since they control this intersection.

90

1500417

Hobart

Bicycle & Pedestrian Facilities

in vicinity of Hobart Middle School

8/19/2019

TAP Chicago UZA (SRTS)

2020

3_CN

$ 247,200

4_High Schedule

*Admin Mod Mar 18*

Q.R. & SPMS shows letting is 8/19/19 (in 2019 TIP)

$ 247,200

18 Q3 - INDOT has issues with Archelogical Report; Probably move 8 months to April 2020. 18 Q4 - Keep in FY 20 per mayor.

102

0710064

Gary

15th Ave

Signals, New or Upgraded

Multiple locations at/near intersection of 15th Ave and MLK Dr,

7/14/2021

STBG I

Chicago UZA

2020

2_RW

$ 160,000

4_High Scope

$ 160,000

18 Q3 - Gary to rescope

Row ID

Des #

Sponsor

Route

Work Type

Location

Letting Date

Federal Fund Type

Year

Phase

In TIP or SPMS

Only

Risk

Comments

TIP 2019

Actual Obligated 2018

TIP 2020

TIP 2021

2022

Post-TIP

Quarterly Notes / Comments

106

1601145

Hammond

Marquette Trail

Bike/Pedestrian Facilities

from State St at Rabin Plaza to Toll Road overpass at Kosciusko St

9/22/2020

CMAQ Chicago UZA

2021

3_CN

$ 1,200,000

2_Low

$ 1,200,000

18 Q3 - On Track

107

1601147

Burns Harbor

Marquette Trail

Bike/Pedestrian Facilities

Marquette Greenway Trail, SR149 to Babcock Rd

8/5/2020

CMAQ Chicago UZA

2021

3_CN

$ 997,934

3_Med Funds

Q3LQR-CN est

$2,049,932 ($1,639,946 fed) CE

$0

$ 997,934

18 Q3 - Alignment set NEPA can be finalized. Q:definition of wetlands (NPS vs DNR). CN Cost increasing (2017 Q4 -TC$1,247,418 [$997,934 fed] to 2018 Q2 TC$1,747,350 [1,397,878 fed] to2018 Q3 TC$2,049,932

[1,639,946 fed]. Schedule favorable candidate for Plan B 2019 letting. CE is $0

108

1601184

Valparaiso

FTA Transfers

CMAQ Demo Operating Assistance

V-Line Porter Hospital (Year #3)

CMAQ Chicago UZA

2021

5_5_FL EX

$ 264,000

1_Zero Obligated

$ 264,000

109

1601185

Valparaiso

FTA Transfers

CMAQ Demo Operating Assistance

CMAQ Demo Chicago DASH Bus #5 (Year #3)

CMAQ Chicago UZA

2021

5_5_FL EX

$ 264,000

1_Zero Obligated

$ 264,000

111

1702158

Gary

Marquette Trail

Bike/Pedestrian Facilities

Gary Green Links/Marquette Trail. Roosevelt St to Polk St.

11/11/2020

STBG I

Chicago UZA

2021

3_CN

$ 1,000,000

2_Low

$ 1,000,000

18 Q3 - RFP process to begin shortly, no PE on Project; Verify PE & CN alotment. PE is owed for $300K May come from CN.

112

9980080

Lake County

45th Ave

Added Travel Lanes

Colfax to W hitcomb St

7/8/2020

STBG I

Chicago UZA

2021

3_CN

$ 7,665,600

2_Low

$ 7,665,600

18 Q3 - NEPA almost finalized; ROW to start soon, on Track

113

1500418

Portage

Marquette Greenway Trail

Bicycle & Pedestrian Facilities

along Ameriplex Drive

8/5/2020

TAP Chicago UZA

2021

3_CN

$ 1,495,560

4_High Funds

$ 1,495,560

18 Q3 - No ROW; TIP shows CN in TAP FHWA; SPMS shows CN in TAP Group I

104

1173427

Crown Point

101st Ave

Roadside Improvements (Drainage)

101st Ave @ SR 53

7/13/2022

STBG I

Chicago UZA

2021

2_RW

$ 200,000

4_High Executive

$ 200,000

18 Q3 - City to decide whether or not to continue with this project. More information at next LQM.

105

1382598

Hobart

County Line Rd

Road Reconstruction (3R/4R Standards)

from US 6 to Cleveland Ave

10/7/2020

STBG I

Chicago UZA

2021

3_CN

$ 6,877,000

4_High Schedule

$ 6,877,000

18 Q3 - NEPA doc is outstanding. FHWA & SHPO have issues. May need to move 12 months. Pedestrian tunnel is not favored by FHWA.

110

1601846

Lake Station

Alternative Fuel Infrastructure

Public Access E-85 & CNG Station. 3P Agreement.

CMAQ Chicago UZA

2021

1_PE

$ 600,385

3_Med Executive Decision

$ 600,385

18 Q3 - City is not sure if they want to continue with this project. 18 Q4 - Flying J not interested in this project. City may decide to contine at a different location

106

1173430

Portage

Central Ave

Road Reconstruction (3R/4R Standards)

Central Ave. reconstruction from Lake/Porter Co. Line to Willowcreek Road

7/8/2020

STBG I

Chicago UZA

2021

3_CN

$ 2,080,000

4_ High Scope

$ 2,080,000

18 Q3 - project will be split in two or more phases by next LQM.

113

1173597

Munster

E-L/Pennsy

Bicycle & Pedestrian

Bike/Ped Trail Connector:

7/14/2021

TAP Chicago

2022

3_CN

$ 784,080

3_Med Funds

In 2019 TIP; Amend

$ 784,080

18 Q3 - CN cost increase TC $980,100 ($784,080 fed) to TC $1,164,403 (931,522 fed) Need a new estimate

Trail

Facilities

Erie-Lackawanna &

UZA

#10 to suspend

since project is being tweaked and may combine with 1173707.

Pennsy Greenway Trails

project and take out of

at Cady Ditch and Marsh

TIP; Keep until next

Ditch

LQM

115

1500222

Hammond

Chicago Ave

Added Travel Lanes

from IN/IL State Line to Marble St (Phase 2)

7/9/2021

STBG I

Chicago UZA

2022

3_CN

$ 6,690,200

2_Low

Q3LQR- CN est

$5,500,000 ($4,400,000 fed); CE

$813,825 ($550,000

fed)= $6 239 326

$ 6,690,200

18 Q3 - On track

116

1500419

Porter County

Calumet Trail

Bicycle & Pedestrian Facilities

Marquette Greenway, Calumet Trail (Phase 5)

1/12/2024

TAP Chicago UZA

2022

1_PE

$ 200,000

3_Low Funds

$ 200,000

18 Q3 - Project to be suspended until later.

117

1601158

Crown Point

109th Ave

Intersect. Improvements (Roundabout)

at Iowa St

7/14/2021

HSIP Chicago UZA

2022

3_CN

$ 1,138,500

2_Low

$ 1,138,500

18 Q3 - City would like to move to FY 20 if possible. INDOT has project in 2021 STIP, but no past TIPs show this earlier than 2022 & not AM or Amend.

118

0710064

Gary

15th Ave

Signals, New or Upgraded

Multiple locations at/near intersection of 15th Ave and MLK Dr,

7/14/2021

STBG I

Chicago UZA

2022

3_CN

$ 716,800

4_High Scope

TC $656,800 fed CN;

$60,000 fed CE

$ 716,800

18 Q3 - Gary to Rescope

114

1382603

Schererville

Kennedy Ave

Added Travel Lanes

Oak St to Junction St

7/13/2023

STBG I

Chicago UZA

2022

2_RW

$ 60,000

4_High Scope

$ 60,000

18 Q3 - On schedule. Part of project may become part of LocalTRAX. More after 19 Q1 LQM.

116

1173594

Porter County

Calumet Trail

Bicycle & Pedestrian

Calumet Trail from Mineral

3/22/2022

TAP Chicago

2022

3_CN

$ 1,862,274

4_High Funds

Q3LQR- CN est

$ 1,862,274

18 Q3 - Not in TIP or in Spending Plan. Project was originally schedulled for FY17, but work by NIPSCO has

Facilities

Springs Rd to SR 49 (Trail

UZA

$1,640,342

delayed this project. Will need PE for new NEPA document (CE-4) and redo most PE.

Rehab)

($1,312,274 fed); CE

$231,293 ($550,000

fed)

117

1173427

Crown Point

101st Ave

Roadside Improvements (Drainage)

101st Ave @ SR 53

7/13/2022

STBG I

Chicago UZA

2023

3_CN

$ 1,096,415

3_Med Executive

$ 1,096,415

18 Q3 - City to decide whether or not to continue with this project. More information at next LQM.

118

1382603

Schererville

Kennedy Ave

Added Travel Lanes

Oak St to Junction St

7/13/2023

STBG I

Chicago UZA

2024

3_CN

$ 8,198,707

3_Med Scope

FY 2024

$ 8,198,707

18 Q3 - Some funds may switch to 1383760; part of project eligable for LocalTRAX. More after 19 Q1 LQM.

Change Orders

Des #

Sponsor

Route

Work Type

Location

Letting Date

Federal Fund Type

Year

CO #

CO amount

Approval date

Comments

Amount for NIRPC

a

9707970

Lake County

45th Ave

Intersect. Improv. W/ Added Turn Lanes

at Colfax St.

8/9/2017

STBG I

Chicago UZA

1

$ 2,018.48

Received 5/29 from DA. Max amount for CO is $35,637.20

CO order Rules (approved TROC 5/29/18): Change Orders are limited to 10% of Contract or $100,000 whichever is less. Maximum amount of all change orders (for the entire program) for a year for the entire year is $375,000.

b

9707970

Lake County

45th Ave

Intersect. Improv. W/ Added Turn Lanes

at Colfax St.

8/9/2017

STBG I

Chicago UZA

2

$ 8,966.93

Received 5/29 from DA. Max amount for CO is $35,637.20

c

Estimated obligations

$ 18,331,671

$ 3,264,262

$ 5,420,931

$ 3,990,600

$ 29,532,232 $ 2,339,040 $ 2,843,811 $ 493,680

$ 18,422,985 $ 2,725,934 $ - $ 1,495,560

$ 7,467,000 $ - $ 1,138,500 $ 2,846,354

$ 9,295,122

Change orders

$ 368,810

$ 6,190

$ 375,000

$ 375,000

$ 375,000

Estimated and actual obligations

$ 18,700,481

$ 3,264,262

$ 5,420,931

$ 3,990,600

$ 29,907,232 $ 2,339,040 $ 2,843,811 $ 493,680 $ 18,797,985 $ 2,725,934 $ - $ 1,495,560 $ 7,842,000 $ - $ 1,138,500 $ 2,846,354 $

9,295,122


2018-2021 fiscal constraint analysis

Obligation authority per funding source per fiscal year

$ 11,951,486

$ 3,607,329

$ 2,901,536

$ 984,647

$ 12,183,049 $ 3,677,222 $ 2,313,202 $ 1,003,725 $ 12,183,049 $ 3,677,222 $ 2,313,202 $ 1,003,725 $ 12,183,049 $ 3,677,222 $ 2,313,202 $ 1,003,725

$ 19,177,198

FY 18 Carryover

$ 342,916

$ 83,082

$ 66,287

$ 23,257

Loans / payback from other UZAs

$ 1,450,000

$ -

$ -

$ -

$ - $ - $ - $ -

$ - $ - $ - $ -

$ - $ - $ - $ -

$ -

Section 164 Penalty (included in with HSIP funds)

FY 19 = $646,110

$ 644,552

$ 644,552

$ 644,552

Prior year obligation authority balance

$ 6,980,644

$ 2,725,616

Total obligation authority

$ 20,725,046

$ 3,690,411

$ 5,693,439

$ 1,007,904

$ 12,183,049

$ 3,677,222

$ 2,957,754

$ 1,003,725

$ 12,183,049

$ 3,677,222

$ 2,957,754

$ 1,003,725

$ 12,183,049

$ 3,677,222

$ 2,957,754

$ 1,003,725

$ 19,177,198

Balance (Obligation authority less estimated and actual obligations)

$ 2,024,565

$ 426,149

$ 272,508

$ (2,982,696)

$ (17,724,183) $ 1,338,182 $ 113,943 $ 510,045 $ (6,614,936) $ 951,288 $ 2,957,754 $ (491,835) $ 4,341,049 $ 3,677,222 $ 1,819,254 $ (1,842,629) $

9,882,076

Grand total obligation authority per fiscal year

$ 31,116,800

$ 19,821,750

$ 19,821,750

$ 19,821,750

Grand total of estimated and actual obligations per fiscal year

$ 31,376,274

$ 35,583,763

$ 23,019,479

$ 11,826,854

Total available obligation authority per fiscal year

$ (259,474)

$ (15,762,013)

$ (3,197,729)

$ 7,994,896

$ 9,882,076


image

image

image

image

image

image

image

Total obligation authority 2018-2021

FY 16 Change Orders =

$ 335,991

FY 17 Change Orders =

$ 182,306

FY 18 Change Orders =

$ 604,636

Average

$ 374,311

FY 16 Change Orders =

$ 335,991

FY 17 Change Orders =

$ 182,306

FY 18 Change Orders =

$ 604,636

Average

$ 374,311

Note: $6,980,644 PYB monies in 2019 are earmarked for 0710056 Total obligations estimated and actual 2018-2021

$ 88,114,750

$ 104,506,261

$ (16,391,511)

September 12, 2018


Northwestern Indiana Regional Planning Commission Notice of Funds Availability – Fall 2018

Multimodal Project Funding

Every year NIRPC receives funding from the Federal Highway Administration for both the Chicago and the Michigan City UZAs. This breakdown is approximately:


Chicago UZA (Group I)

Michigan City UZA (Group II)

STBG

$ 11,951,000

$ 1,165,000

CMAQ

$ 3,607,000

$ 626,000

HSIP

$ 2,270,000

$ 259,000

TA

$ 985,000

$ 98,000

Total

$ 18,813,000

$ 2,148,000


What is available to the Region?


Chicago UZA (Group I)

Michigan City UZA (Group II)

STBG

CMAQ

HSIP

TA

STBG

CMAQ

HSIP

TA

2020

2021

To be completed prior to November 19

2022

2023

2024


Percentages of available funds to be set aside


Chicago UZA (Group I)

Michigan City UZA (Group II)

PE & R/W LID

Risk

Change Orders

PE & R/W LID

Risk

Change Orders

2020

10 %

1%

1 ½ - 2 %

10 %

1%

1 ½ - 2 %

2021

10%

2%

1 ½ - 2%

10%

2%

1 ½ - 2%

2022

10%

3%

1 ½ - 2%

10%

3%

1 ½ - 2%

2023

10%

4%

1 ½ - 2%

10%

4%

1 ½ - 2%

2024

10%

5%

1 ½ - 2%

10%

5%

1 ½ - 2%


For more information about these funding categories, including eligibility requirements, please follow the links below:


Application Schedule


November 19, 2018

Applications are open to LPAs & transit operators for surface transportation projects and transit funding requests.

December 3-14, 2018

Scoping meetings between NIRPC and LPAs

January 4, 2019

Applications are due to NIRPC.

January 4 - 15, 2019

Projects are reviewed by committees & NIRPC.

February 26, 2019

Awarded funds for projects will be announced.


General Guidelines (to be) approved by NIRPC (TPC)

  1. Sponsor must provide NIRPC with a guarantee that their portion of the funding will be available for each phase and year of the project. Sponsors are encouraged to identify funding sources (public & private) that will be used for the sponsor’s portion of the project. This may include innovative financing techniques to ensure success for the project.

  2. The sponsor must provide an ADA/Title VI commitment letter and document if a project will advance progress on implementing their ADA transition plans

  3. Preliminary Engineering and Right of Way phases will be limited to a total of 10

    % of the estimated construction estimate. These funds will set aside for every project. After the completion of the NEPA document, if these funds are not needed, they will be returned to the general fund for future projects within the UZA.

  4. The preliminary engineering (PE) phase must start within the fiscal year in which that phase is programed. This may be paid entirely by the sponsor, or any combination of federal funds and the sponsor’s matching funds. If the sponsor cannot show that this phase has begun within this time frame, the project will risk its programming. The intent is for the sponsor to actually begin the project and work towards a the targeted letting date.

  5. If Right of Way (R/W, ROW) is required and federal funds are involved in this process, it must be completed in the fiscal year that it is programmed. The sponsor may elect not to seek funds for this phase at this time and apply for funds for this phase of the project at a later date.

  6. The application must include a map at sufficient enough scale to clearly identify beginning and ending points of the project. Sponsor’s are encouraged to include photographs or other visuals (on either 8 ½ x 11, 8 ½ x 14, or 11 x 17 paper) to identify the work required and to help explain the project to the reviewers.

    September 12, 2018


  7. The project must let in the fiscal year that it is programed.

    1. Only one exception will be allowed for the letting.

      1. The letting will be allowed to move to the next available year that there is available funding within the existing five-year program.

      2. If the revised letting cannot be made, the project will be eliminated from the TIP, NIRPC’s Spending Plan and lose all current commitment. Future work must wait until the next NOFA and the project will be required compete for future monies. Federal funds spent may or may not be required to be paid back to FHWA by the sponsor.

      3. FHWA guidelines must be followed for Preliminary Engineering. See https://www.fhwa.dot.gov/federalaid/150311.cfm .

  8. The total request for funds must not exceed 50% of the funding available for any given program.

    1. The maximum amount given for all phases for any project for any year will be 50% of the funding category.

    2. In cases where multiple funding category are used, the total amount requested must not exceed 50% of all programs asked.

  9. A project will not be allowed to change its scope in such a way that it appears to be an entirely different project.

    1. Exceptions will be allowed for:

      1. Changes in the project’s limits, upon approval of the Transportation Resources Oversight Committee (TROC).

      2. Downsizing of the scope or breaking the project into several phases, provided the funding request does not increase.

      3. Once a project is awarded, the funds programmed to that project shall remain with that project for the given year. If the project is eliminated or suspended, the funds are subject to reallocation.

  10. If a project is applying for funds from CMAQ or HSIP category, additional requirement must be met. For projects requesting CMAQ funding, please see https://www.fhwa.dot.gov/fastact/factsheets/cmaqfs.cfm . For HSIP funding please see https://safety.fhwa.dot.gov/legislationandpolicy/fast/guidance.cfm .

  11. Technical assistance from NIRPC will be available for these funding sources


Transit Funding Guidelines

TBD