Transportation Resource Oversight Committee Meeting (Lake & Porter Counties)

Tuesday, January 22, 2018 9:00 am CST at NIRPC Office

Agenda


  1. Welcome, Pledge of Allegiance


  2. Meeting Minutes of November 27, 2018

    ACTION REQUESTED: Approval


  3. FY 19-22 Spending Plan Update

    NOTE: Please note that FY 22 needs to be addressed

    ACTION REQUESTED: Informational Only


  4. Project Requests

    1. Scope Change – 1173429 – Lake Station; Intersection Improvement,

      Roundabout

    2. Request for FY 19 PE funding for 1700500 Porter County - $1,000,000

    3. Request for FY 22 CN funding for 1601158 Crown Point - $1,574,000 fed (Initial funding $1,265,000, new amount $2,713,000 Federal)

      ACTION REQUESTED: Vote each item


  5. Letting results Update

    1401030 – Crown Point HSIP Intersection Improvement, Burell Dr & SR 55. Awarded Bid $1,434,443. NIRPC contributed $1,470,030 for CN & CE ACTION REQUESTED: Informational Only


  6. Other New Business

    Q3 Local Quarterly Meetings will be scheduled soon.


  7. Public Comments


  8. Adjournment. Our next meeting is February 26, 2019 @ 9 AM NIRPC Offices


If anyone cannot attend the meeting but would like to participate via teleconference please contact Charles Bradsky at 219-254-2509 or cbradsky@nirpc.org and request the NIRPC’s conference call in number and access code. This request must be made for each meeting and at least 24 hours in advance.

Transportation Resource & Oversight Committee Lake & Porter Counties

6100 Southport Road, Portage November 27, 2018 Meeting Minutes


In attendance were Dean Button (Hammond), John Novacich (Schererville), Mark O’Dell (Chesterton), Chris Anderson (Lake Station), Alex Kutanovski (Crown Point), Chris Anderson (Lake Station), Jill Murr (Cedar Lake), Bob Thompson (Porter County), Denarie Kane (Hobart), George Topoll (Union Township), Marino Solorio (East Chicago), William Allen (East Chicago), Dennis Cobb, Eric Wolverton, Matt Lemon, Steve Stofko, Anthony Schlueter, Jake Dammarell, Ron Wiedeman, Christopher Murphy and Michael Jabo. Joyce Newland (FHWA) participated via conference phone.


NIRPC staff included Charles Bradsky and Candice Eklund.


Charles Bradsky called the meeting to order at 9:02 a.m. with the Pledge of Allegiance.


Approval of Minutes

The minutes of the October 23, 2018 meeting were approved as presented on motion by Dean Button and second by Jill Murr.


FY 19-22 Spending Plan Update

Charles Bradsky informed the Committee there were Congestion Mitigation and Air Quality (CMAQ) funds for one million dollars in the spending plan allocated to Gary Public Transportation Corp (GPTC) in Fiscal Year (FY) 19.

Since GPTC applied these funds in FY 18, these funds will be added to the spending plan for FY 19, leaving a surplus of $1,769,411. Charles discussed the possibility of moving des #1601158 for $112,500, roundabout intersection improvements in Crown Point, with Jake Dammarell. Jake stated the environmental report has been submitted but will need to investigate and contact Charles by November 30th with an answer. Jake notified Charles that the timeline cannot be accelerated. Charles has contacted other LPA’s regarding possibly moving projects forward into FY 19 from FY 20 but they are unable to escalate because it is too late.


Project Requests

  1. Scope change for des #1173429 intersection improvement, roundabout in Lake Station.

    Steve Stofko discussed the roundabout project at Grand Boulevard and Central Avenue in Lake Station. This project has construction costs of $2,044,375, was previously in the 2016-2019 TIP but suspended, and is not in the current TIP. Lake Station has spent some of the federal funds on the project and is requesting to reinstate the project. Steve stated the current road configuration is confusing for traffic and causes accidents. After extensive discussion, the committee agreed to differ this discussion until the January 22, 2019 meeting. The town will supply budget costs for PE, ROW, construction costs and the year(s) funding will be requested.

  2. Request for FY 19 ROW funds for des #1173708 for $80,000 in Crown Point.

    Ron Wiedeman continued the discussion on this project from the prior meeting, stating they did not have a solution for this request. When they originally requested the funding, they were informed by a previous NIRPC employee that funding would be available for their project and to submit the ROW relocations costs when they were acquired. At the time of the original request, the TIP had a four year constraint and now it is a one year constraint. On motion by Jill Murr and second by Dean Button, the committee moved to grant the funds for des #1173708, not to exceed $80,000.

  3. Request for FY 19 ROW funds for DES 1601157 for $154,620 in Crown Point.

    Jake Dammarell continued his discussion from the meeting held on October 23, 2018. This project was originally a placeholder given for ROW based on the estimated value of the land. Since the original request, the land uses changed, which changed the evaluation, resulting in requesting additional funds based on current appraised valued.

    On motion by Jill Murr and second by Dean Button, the committee approved the additional funding of

    $154,620 for des #1601157.

  4. Request for FY 19 CE funds for Des #1382594 for $155,089 in Cedar Lake.

    Jill Murr stated this project has a cost overrun and has a letting date of August 2019. Jill said signals with preemption devices will be installed. These devices will afford Cedar Lake an element of public safety for the residents and visitors to the community and provide a safe ambulance route. On motion by Mark O’Dell and second by Dean Button, the committee approved the funds of $155,089 for des #1382594.

  5. Request FY 19 PL funds for des #1600543 for $36,000.

    NIRPC requested $36,000 to manage the Regional Transportation Improvement Program (RTIP). NIRPC will continue to manage the RTIP for $36,000 annually until 2022, when INDOT will procure the costs. On motion by Denaria Kane and second by Bob Thompson, the committee approved FY 19 funds be given to NIRPC for

    $36,000 to manage the RTIP. Dennis Cobb requested the annual fee of $36,000 be reflected in the spending plan until 2022.

  6. Request for FY 19 PE funding for des #1700500 for $1,000,000 in Porter County.

    Chris Anderson discussed the Willowcreek Road extension project. Chris stated this project is the number three regional priority corridor project identified by NIRPC’s Regional Quarter Study and recommended as an expansion project in the 2040 comprehensive plan. Total construction costs will be 32 million dollars, with phase 1 construction being four million dollars. This project has been awarded $250,000 in federal funding with a local match of 80/20. Porter County requested federal funding to purchase ROW services and acquire land needed for the new alignment. As a requirement, Joyce Newland stated the entire total cost of a project will need to be entered into the RTIP. Joyce will send Charles Bradsky the site for reference. Joyce also stated the discussion cannot continue until the total costs of construction are in the TIP and Porter County present their spending plan. The committee agreed to differ this discussion until the next meeting on January

    22, 2019.


    All approved projects above (letters b – e) total $425,709 in additional FY 2019 spending.

    Dennis Cobb thanked Charles Bradsky for his efforts in updating and maintaining the spending plan.


    Notice of Funding Availability (NOFA)

    Charles Bradsky asked the committee if they had any questions or concerns regarding the NOFA.

    Dean Button questioned if the applicants need to file their ADA Transition Plan and Title 6 plans because they are large files and already located on the town’s website. Charles stated only the certification is required and the applicants can supply NIRPC the link to their website.


    Dennis Cobb raised concerns with the discrepancies between what was presented in the NOFA and what is in the spending plan. Dennis requested adjusting the NOFA document to include what the obligations are so it is known how much money remains in the spending plan. Dennis also questioned the amount of funding that was set aside for risk, believing it was too large. Charles stated he would talk with Trey Wadsworth regarding the committee’s risk factor concerns.


    Letting Results Update

    Charles discussed the winning bid for Merrillville et at, of $2,979,750, which was two percentage points below the engineers estimate. The Section 164 penalty funds that INDOT pays to MPO’s was $284,610 with Prior Year Balances (PYB) of $2,725,616.


    Public Comments

    No public comments were discussed.


    Adjournment

    There being no further business, the meeting adjourned at 10:47 a.m. The next meeting will be held on January 22, 2019 at 9:00 a.m.

    HAPPY HOLIDAYS!



    image

    Blue Text -

    Most recent proposal

    Green Text -

    After discussing with municipal officials, this mu

    Red Text -

    Projects that haven't moved that are at higher ri

    Blue Text -

    Most recent proposal

    Green Text -

    After discussing with municipal officials, this mu

    Red Text -

    Projects that haven't moved that are at higher ri

    Northwestern Indiana Regional Planning Commission

    MPO funds only - 2018-2021 LPA highway projects: Chicago UZA 1/14/2019 < last updated

    Includes all amendment changes & proposed amendment #10 changes


    Row ID

    Row ID

    Des # Sponsor Route Work Type

    Location Letting

    Date

    Federal Fund Type

    Year Phase In TIP or SPMS

    Only

    Risk INDOT PM

    Comments

    TIP 2019

    Actual Obligated 2018

    TIP 2020


    STBG CMAQ HSIP TA STBG CMAQ HSIP TAP/TE-TA


    1. 1600543 NIRPC Regional Planning TIP Software License Fee


      STBG I

      Chicago UZA


      2019 6_6_6_

      UPWP


      $ 36,000 1_Zero Obligated


      $ 36,000


    2. 1601184 Valparaiso FTA

      CMAQ Demo

      V-Line Porter Hospital

      CMAQ Chicago 2019 5_5_FL

      $ 332,800 1_Zero

      $ 332,800

      Transfers

      Operating Assistance

      (Year #1)

      UZA EX

      Obligated


    3. 1601185 Valparaiso FTA


      CMAQ Demo


      CMAQ Demo Chicago


      CMAQ Chicago 2019 5_5_FL


      $ 275,200 1_Zero


      $ 275,200

      Transfers

      Operating Assistance

      DASH Bus #5 (Year #1)

      UZA EX

      Obligated


    4. 1801359 NIRPC CMAQ Planning Public Education SFY


      CMAQ Chicago 2019 6_6_6_


      $ 360,000 1_Zero


      $ 360,000

      2019

      UZA

      UPWP

      Obligated


    5. 1592275 Hobart Environmental Mitigation


      Deep River Stormwater Outfall and BMP.


      7/10/2019 TAP Chicago

      UZA (E&W)


      2019 1_PE $ 36,000 1_Zero KM

      Obligated


      $ 36,000


    6. 1601923 Portage Willowcreek

      Bridge

      Rehabilitate Willowcreek 7/11/2018 STBG I

      2019 3_CN $ 640,000 1_Zero

      JE $ 525,671

      $ 525,671

      Road

      Rehabilitation Or Repair

      Rd Bridge over I-80/90.

      Chicago UZA

      Obligated

    7. 1601164 Hammond Pedestrian Flashing at 3 trail crossings 1/18/2018 HSIP Chicago

      2019 3_CN $ 23,448 1_Zero

      KM Engineer's bid -

      $ 23,448

      $ 23,447

      Beacons, Installed

      UZA

      Obligated

      $232,875 low bid -

      $194,390.29 NIRPC

      obligated

      $174,951.00 for CN

      & $18,039.00 for CE


    8. 1601146 East Chicago Marquette

      Bike/Pedestrian

      from Indinapolis Blvd.

      10/15/2019 CMAQ Chicago 2018 1_PE $ 228,062 1_Zero

      KM 2/1/18 EC to get

      $ 228,062

      Trail

      Facilities

      (US 20) to Kennedy Ave

      UZA

      Obligated

      RFP and contract ASAP to obligate these funds in 2018. 4/3 scoring RFPs 4/25 moved to FY 19 per INDOT/MB


    9. 1500323 Crown Point US 231 Other Intersection

      Improvement


      Courthouse Square, construct pedestrian bump-outs


      7/11/2018 HSIP Chicago

      UZA


      2019 3_CN $ 516,380 1_Zero

      Obligated


      KM Low bid CN

      $529,951.1 ($24,598.40 INDOT) ($454,817 fed); CE

      $68,403.34 ($61,563

      fed)


      $ 516,380


      $ 516,380


    10. 1500416 Hammond US 41 Bike/Pedestrian

Bridge

over US 41 near Conkey St

7/11/2018 TAP Chicago

UZA

2019 3_CN $ 2,000,000 1_Zero KM

Obligated

AM 9/17 Added

$494,000 for CE. Q3LQR- CN est

$4,557,408

$ 2,043,600 $

2,034,400

49 2019 4_CE $ 494,000 1_Zero

Obligated

($2,000,000 fed) CE

$520,000 ($416,000

fed)

$ 416,000 $

416,000

50 1601161 Kouts Regulatory & Warning Sign Replacement

Town-wide

7/11/2018 HSIP Chicago

UZA

2019 3_CN $ 40,500 1_Zero JE

Obligated

Low bid CN

$38,594.08 ($34,735

fed); CE $9,000

$ 34,735

$ 34,735

51 4_CE $ 8,190 1_Zero

Obligated

$ 8,190

$ 8,190


  1. 1601162 Kouts Pavement Markings Town-wide 7/11/2018 HSIP Chicago

    UZA

    2019 3_CN $ 11,700 2_Low JE No bids; to be $ -

    combined in with 1601161 as a CO

  2. 1382594 Cedar Lake Lake Shore

Drive


Intersect.

Improvements (Roundabout)


at Cline Ave 9/12/2018 STBG I Chicago UZA

2019 3_CN $ 1,500,000 1_Zero KM

Obligated


Q3LQR - STG3 CN est $1,722,282.09 ($1,377,825,67 fed) CE $187,500 ($122,174.33 fed)


$ 1,467,373


$ 1,467,373

54 4_CE $ 187,716 $187,716 - $32,627

= $155,089

$ 187,716

$ 187,716

55 1173595 Schererville Pennsy

Greenway

Bicycle & Pedestrian Facilities

Pennsy Greenway P2. Main St to 137th Ave.

3/6/2019 STBG I

Chicago UZA

2019 3_CN $ 680,960

3_ Med KM Funds

Q3LQR - CN est

$870,000 ($696,000 fed) CE $130,500

$ 680,960

56 3/6/2019 STBG I

Chicago UZA


57 3/6/2019 TAP Chicago

UZA

2019 4_CE $ 119,040


2019 3_CN $ 387,000

($104,400 fed) - To be combined with 1382661 and let on one contract.

$ 119,040


$ 387,000

Row ID

Des #

Sponsor

Route

Work Type

Location

Letting Date

Federal Fund Type

Year

Phase

In TIP or SPMS

Only

Risk

INDOT PM

Comments

TIP 2019

Actual Obligated 2018

TIP 2020

58

1382661

Schererville

Pennsy Greenway

Bicycle & Pedestrian Facilities

Pennsy Greenway, P3 from Wilhelm Street at Schererville Town Hall to 213th Street

3/6/2019

STBG I

Chicago UZA

2019

3_CN

$ 1,586,000

3_Med Schedule

KM

Q3LQR - CN est

$1,397,813 ($1,118,250.40 fed) CE $199,687 ($159,749.6 fed) -

To be combined with

$ 1,586,000

59

1401029

Porter County

CR 100S

Intersec. Improvement

CR 100S-2000 W of CR725 Wto 1000 E of CR 500W

3/6/2019

STBG I

Chicago UZA

2019

1_PE

$ 652,000

2_Low

JK

$ 652,000

60

1401030

Crown Point

126th Ave (Burrell Dr)

Intersect. Improv. W/ Added Turn Lanes

From SR 55 to Court St

12/12/2018

HSIP Chicago UZA Sect 164

(100% fed)

2019

3_CN

$ 234,707

2_Low

KM

CE-$155,894 fed

$ 234,707

61

HSIP Chicago UZA

$ 1,191,810

$ 1,191,810

62

1592274

Highland

Signage on multiple trails, installed

Multiple Trails; Multiple LPA's

1/16/2019

TAP Chicago UZA

2019

3_CN

$ 800,000

2_Low

KM

$36,320 ($29,056

fed for CE)

$ 800,000

63

1592420

Merrillville

Install Signal Pre- Emption Devices 1

All signals in Hobart, Crown Point, Schererville, Merrillville, Dyer, Griffith, St. John

11/15/2018

HSIP Chicago UZA Sect 164

(100% fed)

2019

3_CN

$ 1,427,816

2_Low

KM

Combined line 74

with line 75,

(2,135,869

+1017563 =

3,153,432) Q3LQR - CN est $1,752,140 ($1,576,926) CE $0

$ 316,233

$ 316,233

64

PYB Chicago UZA

$ 2,725,616

$ 2,725,616

$ 2,725,616

65

1600418

Gary

Airport Rd

Road Rehab (3R/4R Standards)

Airport Road 3R/4R Reconstruction: Cline Ave to EJ&E RR Bridge Phase 3

1/16/2019

STBG I

Chicago UZA

2019

3_CN

$ 3,500,000

2_Low

KM

verify date January 2019

$ 3,500,000

66

1601157

Crown Point

109th Ave

Access Control

109th Ave Access Control, Delaware Pkwy to SR 53, includes median construction

10/15/2019

HSIP Chicago UZA

2019

2_RW

$ 267,120

2_Low

KM

could this qualify for CMAQ? 11/27 -

Approved by TROC for an adiitional

$154,620 ($112,500

+ 154,620 =

$267,120)

$ 267,120

67

1601159

Valparaiso

Ransom Rd

Other Type Project (Miscellaneous)

Ransom Road Safety Improvements, CR50W to CR 150W

4/3/2019

HSIP Chicago UZA Sect 164

(100% fed)

2019

3_CN

$ 79,170

3_Med Funds

JK

Valpo requesting and additional

$33,741 for CE/CN Q3LQR CN est

$465,800 ($419,220

fed) CE $69,100 ($62,190 fed)

$ 79,170

68

HSIP Chicago UZA

$ 405,108

$ 405,108

69

1601163

Hammond

173rd Ave

Pedestrian Island Construction

at Main Entrance to Purdue NW Campus

8/14/2019

STBG I

Chicago UZA

2019

2_RW

$ 45,000

2-Low

KM

$ 45,000

70

1_PE

$ 27,000

1_Zero Obligated

$ 27,000

$ 24,000

71

1702158

Gary

Marquette Trail

Bike/Pedestrian Facilities

Gary Green Links/Marquette Trail. Roosevelt St to Polk St.

11/11/2020

STBG I

Chicago UZA

2019

1_PE

$ 300,000

2_Low

KM

$ 300,000

72

1601726

Winfield

Randolph St

Other Type Project (Miscellaneous)

Randolph St HAWK Signal (2000' S of 109th)

4/3/2019

HSIP Chicago UZA / Bonus Funds

2019

3_CN

$ 70,200

4_High Schedule

JE

4/3/19 letting

$ 70,200

73

1601727

Winfield

Randolph St

Other Type Project (Miscellaneous)

Randolph St School Zone Flashers (3000' & 4000' S of 109th)

4/3/2019

HSIP Chicago UZA Sect 164

(100% fed)

2019

3_CN

$ 10,000

4_High Schedule

JE

4/3/19 letting

$ 10,000

74

1601728

Winfield

109th Ave

Signage, New or Replacement

109th Ave Signage Improvements (109th, 5600' W of Randolph)

4/3/2019

HSIP Chicago UZA Sect 164

(100% fed)

2019

3_CN

$ 6,000

4_High Schedule

JE

4/3/19 letting

$ 6,000

77

0900080

Portage

Central Ave

Access Control

Willowcreek Rd Intersection Improvements at Central Ave.

3/6/2019

CMAQ Chicago UZA

2019

2_RW

$ 52,000

1_Zero Obligated

JE

$ 52,000

$ 52,000

78

1401034

Hobart

Colorado St

Line of Sight Corrections; Access Management

North of US 30

1/15/2020

HSIP Chicago UZA

2020

2_RW

$ 56,250

4_High Funds

KM

Amend #10 added phase

$ 56,250

79

1592273

Lowell

Bicycle & Pedestrian Equipment

Up to 20 Bicycle Racks

CMAQ Chicago UZA

2019

1_PE

$ 1,600

4_High Executive

KM

to be moved to 2019 per MB. Need to be put into Admin Mod 4/3

$ 1,600

image

Row ID

Des #

Sponsor

Route

Work Type

Location

Letting Date

Federal Fund Type

Year

Phase

In TIP or SPMS

Only

Risk

INDOT PM

Comments

TIP 2019

Actual Obligated 2018

TIP 2020

80

1601158

Crown Point

109th Ave

Intersect. Improvements (Roundabout)

at Iowa St

7/14/2021

HSIP Chicago UZA

2019

2_RW

$ 112,500

4_High Schedule

KM

If PE is in late 2018 & CN is in 2022, RW probably will be moved out to 2020

$ 112,500

81

0710056

Munster

45th St

Railroad Grade Separation & Added Travel Lanes

Reconstruction of 45th St from 0.2 mi E of Calumet Ave to Calumet Ave

3/6/2019

PYB Chicago UZA

2019

3_CN

$ 6,980,644

4_High Schedule Complexity

KM

$ 6,980,644

82

0710056

Munster

45th St

Railroad Grade Separation & Added Travel Lanes

Reconstruction of 45th St from 0.2 mi E of Calumet Ave to Calumet Ave

3/6/2019

STBG I

Chicago UZA

2019

3_CN

$ 2,619,356

4_High Schedule Complexity

KM

*Admin Mod Mar 18* change date from FY 18 to FY 19

$ 2,619,356

83

1601159

Valparaiso

Ransom Rd

Other Type Project (Miscellaneous)

Ransom Road Safety Improvements, CR50W to CR 150W

11/15/2018

HSIP Chicago UZA

2019

2_RW

$ 23,400

JK

RW to be eliminated Amend #10 funds to be applied to CN

84

1601146

East Chicago

Marquette Trail

Bike/Pedestrian Facilities

from Indinapolis Blvd. (US 20) to Kennedy Ave

10/15/2019

CMAQ Chicago UZA

2019

2_RW

$ 24,000

2_Low

KM

No ROW is needed; See Amend #10

85

1601147

Burns Harbor

Marquette Trail

Bike/Pedestrian Facilities

Marquette Greenway Trail, SR149 to Babcock Rd

8/5/2020

CMAQ Chicago UZA

2019

2_RW

$ 12,000

2/8/18 No ROW is needed. See Amend #10

86

1702159

Lake County

101st Ave

Signals, New or Improved

101st Ave New Signals at Sheffield Ave.

7/10/2019

STBG I

Chicago UZA

2018

1_PE

$ 116,000

KM

Project will be completed with local funds only

87

1702159

Lake County

101st Ave

Signals, New or Improved

101st Ave New Signals at Sheffield Ave.

7/10/2019

STBG I

Chicago UZA

2019

2_RW

$ 20,000

3_Med

KM

Project will be completed with local funds only

88

0401062

Schererville

Pennsy Greenway

Bicycle & Pedestrian Facilities

Acquistion

STBG I

Chicago UZA

2019

2_ RR

$ 308,000

2_Low

KM

4/6 Moved from FY 18; per INDOT/JG

89

1601184

Valparaiso

FTA

Transfers

CMAQ Demo Operating Assistance

V-Line Porter Hospital (Year #2)

CMAQ Chicago UZA

2020

5_5_FL EX

$ 326,400

1_Zero Obligated

$ 326,400

90

1601185

Valparaiso

FTA

Transfers

CMAQ Demo Operating Assistance

CMAQ Demo Chicago DASH Bus #5 (Year #2)

CMAQ Chicago UZA

2020

5_5_FL EX

$ 269,600

1_Zero Obligated

$ 269,600

91

1801359

NIRPC

CMAQ Planning

Public Education SFY 2020

CMAQ Chicago UZA

2020

6_6_6_ UPWP

$ 360,000

1_Zero Obligated

$ 360,000

92

1173707

Munster

Pennsy Greenway

Bicycle & Pedestrian Facilities

Construct Pennsy Greenway Trail from Fisher St at Timrick Dr to Calumet Ave north of 45th St

7/10/2019

CMAQ Chicago UZA

2020

3_CN

$ 555,040

2_Low

KM

$ 555,040

93

1173760

Schererville

Kennedy Ave

Added Travel Lanes

Kennedy Ave at Junction St. South to 67th St. and then South to US 30

12/12/2018

STBG I

Chicago UZA

2019

2_RW

$ 200,000

2_Low

KM

$ 200,000

75

1500417

Hobart

Bicycle & Pedestrian Facilities

in vicinity of Hobart Middle School

8/19/2019

TAP Chicago UZA (SRTS)

2020

3_CN

$ 247,200

2_Low

KM

*Admin Mod Mar 18* Q.R.

& SPMS shows letting is 8/19/19 (in 2019 TIP)

$ 247,200

image

Row ID

Des #

Sponsor

Route

Work Type

Location

Letting Date

Federal Fund Type

Year

Phase

In TIP or SPMS

Only

Risk

INDOT PM

Comments

TIP 2019

Actual Obligated 2018

TIP 2020

76

1592275

Hobart

Environmental Mitigation

Deep River Stormwater Outfall and BMP.

7/10/2019

TAP Chicago UZA

2020

3_CN

$ 246,480

2_Low

KM

$ 246,480

94

0900075

Valparaiso

Silhavy Rd

Rebuild 3R/4R

Evans Ave to LaPorte Ave

9/11/2019

STBG I

Chicago UZA

2020

3_CN

$ 3,094,579

2_Low

JK

*Admin Mod Mar 18* change date from FY 21 to FY 19

$ 3,094,579

95

0900075

Valparaiso

Silhavy Rd

Rebuild 3R/4R

Evans Ave to LaPorte Ave

9/11/2019

STBG I

Chicago UZA

2020

4_CE

$ 464,181

2_Low

JK

$ 464,181

96

1802975

Gary

Airport Rd

Other (Street Enhancements)

Airport Road 3R/4R Reconstruction: Cline Ave to EJ&E RR Bridge

7/14/2021

STBG I

Chicago UZA

2020

2_RW

$ 160,000

3-Med

km

18-14; #17

$ 160,000

97

1500221

Hammond

Chicago Ave

Added Travel Lanes

from IN/IL State Line to Marble St

7/10/2019

STBG I

Chicago UZA

2020

3_CN

$ 9,400,000

2_Low

KM

Q3LQR- CN est

$10,000,000 ($8,355,556 fed) CE

$1,305,556 ($1,044,444 Fed) =

$11,791,713($9,433,

369 fed)

$ 9,400,000

98

1601157

Crown Point

109th Ave

Access Control

109th Ave Access Control, Delaware Pkwy to SR 53, includes median construction

10/9/2019

HSIP Chicago UZA

2020

3_CN

$ 1,098,000

2_Low

KM

*Admin Mod Mar 18* LQR,

SPMS shows letting is 10/9/19 (in 2021 TIP) CN est

$1,220,000 ($1,098,000 Fed) CE

$152,000 ($122,000

Fed)

$ 1,098,000

99

1601165

Gary

Regulatory & Warning Sign Replacement

City-wide

7/10/2019

HSIP Chicago UZA

2020

3_CN

$ 450,000

2_Low

KM

$ 450,000

100

0900080

Portage

Central Ave

Access Control

Willowcreek Rd Intersection Improvements at Central Ave.

10/9/2019

CMAQ Chicago UZA

2020

3_CN

$ 914,238

4_High Schedule

JE

*Admin Mod Mar 18* change date from FY 18 to FY 19 Q3LQR-CN est

$1,260,000 ($1,008,000 fed) CE

$ 914,238

101

CMAQ Chicago UZA / Bonus Funds

$ 185,762

$ 185,762

102

1172007

Lake County

45th Ave

Added Travel Lanes

45th Ave. from Whitcomb to Chase (Ph 2B)

7/10/2019

STBG I

Chicago UZA

2020

3_CN

$ 1,752,000

4_High Schedule

KM

high risk for FY 19; CN est $1,950,000 ($1,560,000 Fed) CE

$243,750 ($192,000

fed)

$ 1,752,000

103

1382598

Hobart

County Line Rd

Road Reconstruction (3R/4R Standards)

from US 6 to Cleveland Ave

10/7/2020

STBG I

Chicago UZA

2020

2_RW

$ 200,000

4_High Schedule

KM

$ 200,000

104

1401034

Hobart

Colorado St

Line of Sight Corrections; Access Management

North of US 30

1/15/2020

HSIP Chicago UZA / Bonus Funds

2020

3_CN

$ 734,850

4_High Funds

KM

*Admin Mod Mar 18* LQR, SPMS

shows letting is 10/19/19 (in 2021 TIP)

$ 734,850

105

1702159

Lake County

101st Ave

Signals, New or Improved

101st Ave New Signals at Sheffield Ave.

7/10/2019

STBG I

Chicago UZA

2020

3_CN

$ 391,000

3_ Med Schedule

KM

Q3LQR- CN

$500,000 ($400,000

fed) CE $75,000 ($3,000 fed)

$ -

106

0710064

Gary

15th Ave

Signals, New or Upgraded

Multiple locations at/near intersection of 15th Ave and MLK Dr,

7/14/2021

STBG I

Chicago UZA

2020

2_RW

$ 160,000

4_High Scope

KM

18-14; #17

$ -

107

1172078

Gary

Ridge Rd

Road Reconstruction (3R/4R Standards)

Ridge Road Reconstruction, Connecticut St to Mississippi St. Phase 2

7/10/2019

STBG I

Chicago UZA

2020

3_CN

$ 5,060,000

4_High Scope

KM

18-14; #17

$ -

image

Row ID

Des #

Sponsor

Route

Work Type

Location

Letting Date

Federal Fund Type

Year

Phase

In TIP or SPMS

Only

Risk

INDOT PM

Comments

TIP 2019

Actual Obligated 2018

TIP 2020

108

1601184

Valparaiso

FTA

Transfers

CMAQ Demo Operating Assistance

V-Line Porter Hospital (Year #3)

CMAQ Chicago UZA

2021

5_5_FL EX

$ 264,000

1_Zero Obligated

JK

109

1601185

Valparaiso

FTA

Transfers

CMAQ Demo Operating Assistance

CMAQ Demo Chicago DASH Bus #5 (Year #3)

CMAQ Chicago UZA

2021

5_5_FL EX

$ 264,000

1_Zero Obligated

JK

110

1173760

Schererville

Kennedy Ave

Added Travel Lanes

Kennedy Ave at Junction St. South to 67th St. and then South to US 30

2/5/2020

STBG I

Chicago UZA

2020

3_CN

$ 4,206,472

2_ Low Funds

KM

Q3LQR- CN est

$5,834,000 ($4,206,472[72%]) CE $875,000 ($0

fed)

111

1702158

Gary

Marquette Trail

Bike/Pedestrian Facilities

Gary Green Links/Marquette Trail. Roosevelt St to Polk St.

11/11/2020

STBG I

Chicago UZA

2021

3_CN

$ 1,000,000

2_Low

KM

112

9980080

Lake County

45th Ave

Added Travel Lanes

Colfax to Whitcomb St

7/8/2020

STBG I

Chicago UZA

2021

3_CN

$ 7,665,600

2_Low

KM

113

1801738

Gary

Lake Street

Complete Streets Enhancement

US 12/20 & Lake St., north

7/14/2020

STBG I

Chicago UZA

2021

3_CN

$ 2,060,000

2_Low

KM

114

1601145

Hammond

Marquette Trail

Bike/Pedestrian Facilities

from State St at Rabin Plaza to Toll Road overpass at Kosciusko St

9/22/2020

CMAQ Chicago UZA

2021

3_CN

$ 1,200,000

2_Low

KM

115

1500418

Portage

Marquette Greenway Trail

Bicycle & Pedestrian Facilities

along Ameriplex Drive

8/5/2020

TAP Chicago UZA

2021

3_CN

$ 1,495,560

2_Low

JE

116

1601146

East Chicago

Marquette Trail

Bike/Pedestrian Facilities

from Indinapolis Blvd. (US 20) to Kennedy Ave

10/15/2019

CMAQ Chicago UZA

2020

3_CN

$ 828,000

3_Med Schedule

KM

Amend #10 added phase

117

pending

Gary

Airport Rd

Other (Street Enhancements)

Airport Road 3R/4R Reconstruction: Cline Ave to EJ&E RR Bridge Phase IV

1/16/2019

STBG I

Chicago UZA

2020

2_RW

$ 160,000

3_Med Scope

KM

18-14; #17

118

1601163

Hammond

173rd Ave

Pedestrian Island Construction

at Main Entrance to Purdue NW Campus

8/14/2020

HSIP Chicago UZA

2021

3_CN

$ 1,029,250

3_Med Funds

KM

Q3LQR- CN est

$573,913 ($459,130 fed); CE $56,087 ($68,870 fed) FY 19

Q1 est $895,000

($805,500 fed) CE

$134,250 ($120,825

fed)

119

1601147

Burns Harbor

Marquette Trail

Bike/Pedestrian Facilities

Marquette Greenway Trail, SR149 to Babcock Rd

8/5/2020

CMAQ Chicago UZA

2021

3_CN

$ 997,934

4_High Funds, Schedule

Q3LQR-CN est

$2,049,932 ($1,639,946 fed) CE

$0

120

1173430

Portage

Central Ave

Road Reconstruction (3R/4R Standards)

Central Ave. reconstruction from Lake/Porter Co. Line to Willowcreek Road

7/8/2020

STBG I

Chicago UZA

2020

2_RW

$ 200,000

4_High Scope

JE

*Admin Mod Mar 18* change date from FY 18 to FY 20

121

1006787

Merrillville

Mississippi St

Added Travel Lanes

93rd Ave to 101st Ave

7/8/2020

STBG I

Chicago UZA

2021

3_CN

$ 3,612,000

4_Funds

KM

Amend #10 added phase CN est

$4,516,000 ($3,612,000 fed) CE

$0

122

1382598

Hobart

County Line Rd

Road Reconstruction (3R/4R Standards)

from US 6 to Cleveland Ave

10/7/2020

STBG I

Chicago UZA

2021

3_CN

$ 6,877,000

4_High Schedule

KM

123

1601846

Lake Station

Alternative Fuel Infrastructure

Public Access E-85 & CNG Station. 3P Agreement.

CMAQ Chicago UZA

2021

1_PE

$ 600,385

3_Med Executive Decision

KM

124

1173430

Portage

Central Ave

Road Reconstruction (3R/4R Standards)

Central Ave. reconstruction from Lake/Porter Co. Line to Willowcreek Road

7/8/2020

STBG I

Chicago UZA

2021

3_CN

$ 2,080,000

4_ High Scope

JE

125

1173427

Crown Point

101st Ave

Roadside Improvements (Drainage)

101st Ave @ SR 53

7/13/2022

STBG I

Chicago UZA

2021

2_RW

$ 200,000

4_High Executive

KM

image

Row ID

Des #

Sponsor

Route

Work Type

Location

Letting Date

Federal Fund Type

Year

Phase

In TIP or SPMS

Only

Risk

INDOT PM

Comments

TIP 2019

Actual Obligated 2018

TIP 2020

126

1173597

Munster

E-L/Pennsy Trail

Bicycle & Pedestrian Facilities

Bike/Ped Trail Connector: Erie- Lackawanna & Pennsy Greenway Trails at Cady Ditch and Marsh Ditch

7/14/2021

TAP Chicago UZA

2022

3_CN

$ 784,080

3_Med Funds

KM

In 2019 TIP; Amend

#10 to suspend project and take out of TIP; Keep until next LQM

127

1500222

Hammond

Chicago Ave

Added Travel Lanes

from Marble St to Baltimore Ave(Phase 2)

7/9/2021

STBG I

Chicago UZA

2022

3_CN

$ 4,950,000

2_Low

KM

Q3LQR- CN est

$5,500,000 ($4,400,000 fed); CE

$813,825 ($550,000

128

1601158

Crown Point

109th Ave

Intersect. Improvements (Roundabout)

at Iowa St

7/14/2021

HSIP Chicago UZA

2022

3_CN

$ 1,138,500

2_Low

KM

129

1802975

Gary

Airport Rd

Other (Street Enhancements)

Airport Road 3R/4R Reconstruction: Cline Ave to EJ&E RR Bridge Phase IV

7/14/2021

STBG I

Chicago UZA

2022

3_CN

$ 716,800

2_Low

KM

18-14; #17

130

1802973

Gary

15th Ave

Road Reconstruction

I-65 to MLK Dr.; including Michigan St. & Texas St.

7/14/2021

STBG I

Chicago UZA

2022

3_CN

$ 3,000,000

2_Low

KM

18-14; #17

131

1500419

Porter County

Calumet Trail

Bicycle & Pedestrian Facilities

Marquette Greenway, Calumet Trail (Phase 5)

1/12/2024

TAP Chicago UZA

2022

1_PE

$ 200,000

3_Low Funds

JK

132

1382603

Schererville

Kennedy Ave

Added Travel Lanes

Oak St to Junction St

7/13/2023

STBG I

Chicago UZA

2022

2_RW

$ 60,000

4_High Scope

KM

133

1173594

Porter County

Calumet Trail

Bicycle & Pedestrian Facilities

Calumet Trail from Mineral Springs Rd to SR 49 (Trail Rehab)

3/2/2022

TAP Chicago UZA

2022

3_CN

$ 1,862,274

4_High Funds

JK

Q3LQR- CN est

$1,640,342 ($1,312,274 fed); CE

$231,293 ($550,000

fed)

134

0710064

Gary

15th Ave

Signals, New or Upgraded

Multiple locations at/near intersection of 15th Ave and MLK Dr,

7/14/2021

STBG I

Chicago UZA

2022

3_CN

$ 716,800

4_High Scope

KM

18-14; #17

135

1173427

Crown Point

101st Ave

Roadside

Improvements (Drainage)

101st Ave @ SR 53

7/13/2022

STBG I

Chicago UZA

2023

3_CN

$ 1,096,415

3_Med

Executive

KM

136

1382010

Portage

Samuelson Road

Road Reconstruction (3R/4R Standards)

Centeral Ave to Portage Ave

7/13/2022

STBG I

Chicago UZA

2023

3_CN

$ 3,000,000

Estimated

137

1500419

Porter County

Calumet Trail

Bicycle & Pedestrian Facilities

Marquette Greenway, Calumet Trail (Phase 5)

1/12/2024

TAP Chicago UZA

2024

1_PE

$ 1,400,000

3_Low Funds

JK

138

1382603

Schererville

Kennedy Ave

Added Travel Lanes

Oak St to Junction St

7/13/2023

STBG I

Chicago UZA

2024

3_CN

$ 8,198,707

3_Med Scope

KM

FY 2024

image



image

Row ID

Row ID

Des # Sponsor Route Work Type


Location Letting

Date


Federal Fund Type


Year Phase In TIP or SPMS

Only


Risk INDOT PM


Comments


TIP 2019


Actual Obligated 2018


TIP 2020


Change Orders


Des # Sponsor Route Work Type Location Letting

Date


Federal Fund Type


Year CO # CO amount


Approval date


Comments Amount for NIRPC

  1. 1601164 Hammond Pedestrian Flashing at 3 trail crossings 1/18/2018 HSIP Chicago

    2019 CO #1 $ 6,190

    concurrence sent to

    Total amount

    $ 6,190

    $ 6,190

    Beacons, Installed

    UZA

    Hammond on 5/3/2018

    $6,878 ($6190.2 fed)


  2. 9707970 Lake County 45th Ave Intersect. Improv.

    W/ Added Turn Lanes

    at Colfax St. 8/9/2017 STBG I Chicago UZA

    1 $ 2,018.48 Received 5/29 from DA. Max amount for CO is $35,637.20

    $ 2,018.48

    $ 2,018

    CO order Rules (approved TROC 5/29/18): Change Orders are limited to 10% of Contract or $100,000 whichever is less. Maximum amount of all change orders (for the entire program) for a year for the entire year is $375,000.


  3. 9707970 Lake County 45th Ave Intersect. Improv.

    W/ Added Turn Lanes

    at Colfax St. 8/9/2017 STBG I Chicago UZA

    2 $ 8,966.93 Received 5/29 from DA. Max amount for CO is $35,637.20

    $ 8,966.93

    $ 8,967


  4. 1601161 Kouts Regulatory & Warning Sign Replacement (Pavement Markings)

    Town-wide 7/11/2018 HSIP Chicago UZA

    2019 1 $ 8,323.70

    email sent to J. Sergent 12/5/18

    Total for CO

    =$9,248.56 This is to add CN of 1601162 to T-40228

    approved TROC

    $ 8,324

    $ 8,324

  5. 1601161 Kouts Regulatory & Warning Sign Replacement (Pavement Markings)

    Town-wide 7/11/2018 HSIP Chicago UZA

    2019 2 $ 8,190.00 this is additional CE

    for 1601162 being added to T-40228 TROC approved

    $3,376 10/23

    $ 3,376

    $ 3,376

  6. 1173708 Crown Point Summit St Intersect. Improv.

W/ Added Turn Lanes

Summit St & Merrillville Rd

7/8/1905 CMAQ Chicago 2019 1 $ 47,406.00 UZA


Estimated obligations

$ 18,926,760

$ 1,249,662

$ 6,057,467

$ 3,682,600

$ 15,070,760

$ 2,611,040

$ 2,282,850

$ 493,680

Total Change Orders

'*1

$ 346,125

$ 28,875

$ 375,000

Estimated and actual obligations

$ 18,955,635

$ 1,249,662

$ 6,057,467

$ 3,682,600

$ 15,445,760

$ 2,611,040

$ 2,282,850

$ 493,680

Obligation authority per funding source per fiscal year

$ 11,951,486

$ 3,607,329

$ 2,901,536

$ 984,647

$ 12,183,049

$ 3,677,222

$ 2,313,202

$ 1,003,725

FY 18 Carryover

$ 342,916

$ 83,082

$ 66,287

$ 23,257

2018-2021 fiscal constraint analysis

Loans / payback from other UZAs

$ 1,450,000

$ -

$ -

$ -

$ -

$ -

$ -

$ -

Section 164 Penalty (included in with HSIP funds) (See table at X185)

FY 19 = $646,110

$ 644,552

Bonus Funds from INDOT ([FY19-1601726,1601727,1601728][FY20-1401034, 0900080])

$920,612

$ 185,762

$ 734,850

Prior year obligation authority balance

$ 6,980,644

$ 2,725,616

Total obligation authority

$ 20,725,046

$ 3,690,411

$ 5,693,439

$ 1,007,904

$ 12,183,049

$ 3,862,984

$ 3,692,604

$ 1,003,725

Balance (Obligation authority less estimated and actual obligations)

$ 1,769,411

$ 2,440,749

$ (364,028)

$ (2,674,696)

$ (3,262,711)

$ 1,251,944

$ 1,409,754

$ 510,045

Grand total obligation authority per fiscal year

$ 31,116,800

$ 20,742,362

Grand total of estimated and actual obligations per fiscal year

$ 29,945,364

$ 20,833,330

Total available obligation authority per fiscal year

$ 825,311

$ (465,968)

*1

On Sept 18, TROC voted to move $123,474 from FY 19 C.O.s to bottom line to balance budget

image

st stay where it is. sk


TIP 2021

2022

TIP 2023

2024

Post-2024

Quarterly Notes / Comments

STBG

CMAQ

HSIP

TA

STBG

CMAQ

HSIP

TA

STBG

CMAQ

HSIP

TA

STBG

CMAQ

HSIP

TA

All sources

18 Q3 - On Schedule

18 Q3 - In Contracts. Letting Low bid $657,088.16 ($525,671 fed) CE- $0.00

18 Q3 - Had trouble getting RFP for PE. Would like to move funding to FY 19…but NIRPC does not have the funds.

18 Q3 - In Contracts. INDOT wants city to add ped signals; to be paid for by INDOT. Verify this when contract lets. Winning contact $529,951.10

18 Q3 - $494,000 for CE given by Gary Evers (AM 9/17), but not in TIP or Spending Plan; Discuss at TROC

18 Q3 - $494,000 for CE given by Gary Evers (AM 9/17), but not in TIP or Spending Plan; Discuss at TROC

18 Q3 - In Contracts CE? Originally put CE in with PE (big No-No) for CE is $9,100 TC ($8,190 fed) Winning bid at letting is $38594.08 ($34,735 fed)

18 Q3 - In Contracts CE? Originally put CE in with PE (big No-No) for $9,100 TC ($7,280)

18 Q3 - STG 3 revised in Permits, ROW good. Minor Q: with Hydraulics. No big issues

18 Q3 - costs are up but town will cover. 10/12/18 The town wishes to eliminate this project and apply all funds to 1382661

19 Q3 - costs are up but town will cover.

TIP 2021

2022

TIP 2023

2024

Post-2024

Quarterly Notes / Comments

18 Q3 - Will move RR funds from 0401062. AM to come later. Some RR issues. 10/12/18 The town wishes to eliminate 0401062 and apply all funds to this project ($308,000 + $1,176,838 = $1,484,838)

18 Q3 - HSIP funds?? SPMS shows $652,000 Group I funds and $427,888 Group IV funds

18 Q3 - ROW is on track; 6/22 STG 3 estimate CN $1.54 M total & CE $192K total ($1,558,800 HSIP funds) Need $156K

18 Q3 - Letting moving to 1/16/19 because of NEPA doc, STG 3 due 8/24/18, RFC is 11/7/18. 18 Q4 - GTG

18 Q3 - Minimal Risk. Move letting one month (to 10/11/18) due to agreement with RR at one location.

New estimate CN - TC $3,628,767 $2,725,616 is PYB monies. See email strings on 2/23

18 Q3 - Gary want to accelerate to FY 19 (April '19) but told that may not happen; TROC to discuss.

18 Q3 - On schedule; City would like to accelerate if possible 11/27 - Approved by TROC for an adiitional $154,620 ($112,500 + 154,620 = $267,120)

18 Q3 - Accelerated from 11/20. City would like additional funds for Mill & Fill, & Rumble Stripes to be discussed at TROC. 19 Q1 - new estimate CN $ 50,4500 ($454,050 fed) CE $ 63,063 ($56,757 fed) However only $476, 361 (fed) allocated.

18 Q3 - May not need; but keep on the books just in case. funding moved to HSIP, will be at 90/10, so new estimate is CN $891,000 (fed)

funding moved to HSIP, will be at 90/10, so new estimate is CN $891,000 (fed)

18 Q3 - On schedule

18 Q3 - All projects on one CN contract. CN cost increased from TC $78,000 ($70,200 fed) to TC $125,000 ($112,500 fed). Candidate for Plan B 2019 letting.

18 Q3 - All projects on one CN contract. CN cost increased from TC $10,000 ($9,000 fed) to TC $16,000 ($14,400 fed). Candidate for Plan B 2019 letting.

18 Q3 - All projects on one CN contract. CN cost increased from TC $6,000 ($5,400 fed) to TC $8,000 ($7,200 fed). Candidate for Plan B 2019 letting.

Admin Mod 9/17 added funds to this project. From $1,089,760 to $1,152,000 (fed) 18 Q3 - ROW in Condemnation; STG3 6/18;

18 Q3 - ROW current needs equal $195,000. 18 Q4 - Project costs are starting to escalate. ROW- 4X; CN- 2X. Advised to talk to INDOT since they control this intersection.

18 Q3 - Town still wants to continue but informed that there may not be funds.

image

TIP 2021

2022

TIP 2023

2024

Post-2024

Quarterly Notes / Comments

18 Q3 - City would like to move this phase to FY 20

18 Q3 - INDOT, RDA, NIRPC funds. Moving along, USPs better; big issue with shoefly (RR want town to build, INDOT feels not a good idea). If it getts bumped, it will probably be to FY 22 or 23.

18 Q3 - INDOT, RDA, NIRPC funds. Moving along, USPs better; big issue with shoefly (RR want town to build, INDOT feels not a good idea).

N/A

18 Q3 - I parcel of ROW is needed, agreement with NIPSCO no purchase

N/A

Eliminate the project per DA. County will do on their own. Per email on 9/20

18 Q3 - keep here, Revisit next LQM. Eliminate the project per DA. County will do on their own. Per email on 9/20

18 Q3 - Will move these funds to 1382661 [phase 3], but waiting until Phase 3 is ready. AM to come later.

18 Q3 - Need a new estimate since project is being tweaked and may combine with 1173597. Funds may move to 1173597 and move to 2022.

18 Q3 - Costs are up but keep funding the same. Some funding may come from 1382603.

18 Q3 - INDOT has issues with Archelogical Report; Probably move 8 months to April 2020. 18 Q4 - Keep in FY 20 per mayor.

image

TIP 2021

2022

TIP 2023

2024

Post-2024

Quarterly Notes / Comments

18 Q3 - On track. 18 Q4 - Cost are expecting to rise.

18 Q3 - ROW has 2 condemnations; CN RR

18 Q3 - ROW has 2 condemnations; CN RR

18 Q3 - Funds for RR are in PE

18 Q3 - City would like to accelerate if possible.

18 Q3 - RFP in process

10/19/18 - Portage wishes to move the project one year because of R/W issues

18 Q3 - Lake County wants to move to FY 20; need to verify ROW amounts

18 Q3 - NEPA doc is outstanding. FHWA & SHPO have issues. May need to move 12 months.

18 Q3 - ROW current needs equal $195,000 18 Q4 - Updated ROW cost are $571,000, updated CN cost is

$1,620,000 18 Q4 - Project costs are starting to escalate. Advised to talk to INDOT since they control this intersection. 19 Q1 - Scaled back project, removed drainage issues (to be handled by INDOT). new estimate CN $1,545,000 ($1,390,500 fed) & CE $185,400 ($166,860)

18 Q3 - keep here, Revisit next LQM. Eliminate the project per DA. County will do on their own. Per email on 9/20

18 Q3 - Gary to rescope

image

TIP 2021

2022

TIP 2023

2024

Post-2024

Quarterly Notes / Comments

$ 264,000

$ 264,000

$ 4,206,472

18 Q3 - Costs are up but keep funding the same. Some funding may come from 1382603.

$ 1,000,000

18 Q3 - RFP process to begin shortly, no PE on Project; Verify PE & CN alotment. PE is owed for $300K May come from CN.

$ 7,665,600

18 Q3 - NEPA almost finalized; ROW to start soon, on Track

$ 2,060,000

$ 1,200,000

18 Q3 - On Track

$ 1,495,560

18 Q3 - No ROW; TIP shows CN in TAP FHWA; SPMS shows CN in TAP Group I

$ 828,000

19 Q1 - Letting needs to move to FY21.

$ 160,000

18 Q3 - Gary to rescope, was previously 1600418, but needs a new des #

$ 1,029,250

18 Q3 - City requesting additional funds for scope revision (bus turnout spot) PE and CN. CN est $573,913 ($459,130 fed); CE $56,087 ($68,870 fed) 19 Q1 LQR- CN est $895,000 ($716,000 fed); CE $134,250 ($88,000

fed) OK to move to FY 21 per DB 10/19/18; funding moved to HSIP, will be at 90/10, so new estimate is CN $891,000 (fed)

$ 997,934

18 Q3 - Alignment set NEPA can be finalized. Q:definition of wetlands (NPS vs DNR). CN Cost increasing (2017 Q4 -TC$1,247,418 [$997,934 fed] to 2018 Q2 TC$1,747,350 [1,397,878 fed] to2018 Q3 TC$2,049,932

[1,639,946 fed]. CE is $0 19 Q1 - moving to FY 22

$ 200,000

18 Q3 - project will be split in tow or more phases by next LQM.

$ 3,612,000

18 Q3 - Good. Minimal risk to schedule, funds or scope. Candidate for Plan B 2019 letting. 18 Q4 - Town would like to move this project back one year to come up with the money and get more life out of pavment.

$ 6,877,000

18 Q3 - NEPA doc is outstanding. FHWA & SHPO have issues. May need to move 12 months. Pedestrian tunnel is not favored by FHWA.

$ 600,385

18 Q3 - City is not sure if they want to continue with this project. 18 Q4 - Flying J not interested in this project. City may decide to contine at a different location

$ 2,080,000

18 Q3 - project will be split in two or more phases by next LQM. 19 Q1 - on Hold until after election, further notice.

$ -

18 Q3 - City to decide whether or not to continue with this project. More information at next LQM. 19 Q1

- City wishes to eliminate project; will eliminate Jan 2019

image

TIP 2021

2022

TIP 2023

2024

Post-2024

Quarterly Notes / Comments

$ 784,080

18 Q3 - CN cost increase TC $980,100 ($784,080 fed) to TC $1,164,403 (931,522 fed) Need a new estimate since project is being tweaked and may combine with 1173707.

$ 4,950,000

18 Q3 - On track

$ 1,138,500

18 Q3 - City would like to move to FY 20 if possible. INDOT has project in 2021 STIP, but no past TIPs show this earlier than 2022 & not AM or Amend.

$ 716,800

18 Q3 - Gary to rescope, was previously 1600418, but needs a new des #

$ 3,000,000

$ 200,000

18 Q3 - Project to be suspended until later.

$ 60,000

18 Q3 - On schedule. Part of project may become part of LocalTRAX. More after 19 Q1 LQM.

$ 1,862,274

18 Q3 - Not in TIP or in Spending Plan. Project was originally schedulled for FY17, but work by NIPSCO has delayed this project. Will need PE for new NEPA document (CE-4) and redo most PE. 18 Q4 - OK to move to FY 23 19 Q1 new CN amount $1,640,342 ($1,312,374 fed); CE $231,293 ($185,035 fed); Total

$1,871,635 (1,497,308 fed)

$ -

18 Q3 - Gary to Rescope

18 Q3 - City to decide whether or not to continue with this project. More information at next LQM. 19 Q1 - City wishes to eliminate project; will eliminate Jan 2019

$ 3,000,000

$ 1,400,000

$ 8,198,707

18 Q3 - Some funds may switch to 1383760; part of project eligable for LocalTRAX. More after 19 Q1 LQM.

image

TIP 2021

2022

TIP 2023

2024

Post-2024

Quarterly Notes / Comments

$ 12,868,107

$ 3,553,934

$ -

$ 1,495,560

$ 25,349,400

$ -

$ 1,138,500

$ 984,080

$ 4,862,274

$ -

$ -

$ -

$ 9,598,707

$ -

$ -

$ -

$ -

$ 375,000

$ 375,000

$ 375,000

$ 375,000

$ 13,243,107

$ 3,553,934

$ -

$ 1,495,560

$ 25,724,400

$ -

$ 1,138,500

$ 984,080

$ 5,237,274

$ -

$ -

$ -

$ 9,973,707

$ -

$ -

$ -

$ -

$ 12,183,049

$ 3,677,222

$ 2,313,202

$ 1,003,725

$ 12,183,049

$ 3,677,222

$ 2,313,202

$ 1,003,725

$ 12,183,049

$ 3,677,222

$ 2,313,202

$ 1,003,725

$ 12,183,049

$ 3,677,222

$ 2,313,202

$ 1,003,725

$ 19,177,198

$ -

$ -