Transportation Resource Oversight Committee Meeting (Lake & Porter Counties)
Wednesday, December 11, 2019
9:00 am CST at NIRPC Office, Lake Michigan Room
Agenda
Call to Order by Chairman and Pledge of Allegiance
Public Comments
This is an opportunity for comments from members of the audience. The amount of time available to speak will be limited to 3 minutes. Commenters must indicate their wish to comment on the sign-in sheet.
2020-2024 Transportation Improvement Program
1173430 (Schererville – Kennedy Ave) & 16001146 (East Chicago – Marquette Geenway Trail) need to move out of FY 21. This creates a huge surplus in FY 21. The table on the following page shows the current requests for funding / schedule movement:
ACTION REQUESTED: Approval
Adjournment.
The next regularly scheduled TROC Lake/Porter Meeting is scheduled for February 25, 2020 at 9 a.m. in the Lake Michigan Room at the NIRPC office.
Requests for possible funding / schedule movement (as of 12/5/19) | ||||||||
Des # | LPA | Project description | Phase | Funding Yea | Total $ | Fed $ | Comments / Requested Movement | |
1 | 1173430 | Schererville | Kennedy Ave | CN | FY 21 | $ 5,258,090 | $ 4,206,472 | Move from FY 21 to FY 25/26 |
2 | 16001146 | East Chicago | Marquette Greenway Trail, Indinapolis Blvd to Kennedy Ave | CN | FY 21 | $ 1,035,000 | $ 828,000 | Move from FY 21 to FY 22/23 |
3 | 1902686 | Valparaiso | Intersection Improvement/ Lincolnway and Campbell St. | PE | FY 23 | $ 400,000 | $ 320,000 | Move to FY 21 from FY 23 |
4 | 1601147 | Burns Harbor | Marquette Greenway Trail | CN | FY 21 | $ 2,064,930 | $ 1,651,944 | Scribner's error in TIP; award reduced to 48% ($997,934) |
5 | 1902675 | Lake County Parks | Veterans Trail; 113th to Iowa | CN | FY 24 | $ 1,342,754 | $ 1,074,203 | Move to FY 21 from FY 24 |
6 | 1006787 | Merrillville | Added Travel Lanes; Mississippi St from 93rd to 101st | CE | CN in FY 21 | $ 520,000 | $ 416,000 | Funds not previously requested |
7 | 1901949 | Merrillville | Added Sidewalks: Broadway from 73rd to 80th (US 30) | CE | CN in FY 21 | $ 86,800 | $ 69,440 | Funds not previously requested |
8 | 1500222 | Hammond | Chicago St | CN | FY 23 | $ 6,175,500 | $ 4,940,400 | Move to FY 21 from FY 23 (Combine movement with 1601145) |
9 | 1601145 | Hammond | Marquette Greenway Trail | CN | FY 21 | $ 1,500,000 | $ 1,200,000 | Move from FY 21 to FY 23 (Combine movement with 1500222) |
10 | 1401034 | Hobart | Sight Correction; Colorado St & US 30 | CN | FY 25+ | ?? | ?? | Project accelerate to FY 21 from FY 25+ |
11 | 1382598 | Hobart | County Line Rd & 700 | ROW | CN in FY 21 | ?? | ?? | Currently has $200,000 for ROW in FY 20 |
12 | 1902707 | Hobart | Marcella Dr & 61st Ave | ROW | CN in FY 23 | ?? | ?? | Originally asked for $224,430 for ROW but not awarded. |
13 | 1601158 | Crown Point | Roundabout:109th & Iowa | CN | Not in TIP | $ 2,325,000 | $ 2,092,500 | CP had originally said that they would construct with 100% Local funds |